Create Your Project's Work Breakdown Structure
Background
After creating a new project in your company's Procore account, you can use the built-in WBS features to define the cost structure for Procore's Project Financials tools. When defining a project's WBS cost structure, you have two choices. If you are unsure which choice to make, contact your company's Procore administrator for guidance:
Apply your company's default WBS. This is the WBS defined by your company's Procore administrator and you can use it exactly as it was created.
Copy the WBS from another project. This is the WBS defined on one of your existing Procore project templates. Keep in mind that you can create a unique WBS for each project in your company's account. In order to copy the WBS from another source project to your new target project, you must first save the source project as a project template. See Configure a project template.
Things to Consider
Required User Permissions:
'Admin' level permissions on the Project level Admin tool.
Additional Information:
The Project level 'work breakdown structure' page is similar to the Company level page. The primary differences are:
You cannot add custom segments at the Project level. They must always be added at the Company level. See Add custom segments.
You cannot edit the budget code structure at the Project level. The budget code structure is always defined at the Company level. See Arrange the company budget code structure.
You cannot add sub jobs at the Company level. Sub jobs are always added at the Project level. See Enable sub jobs on projects for WBS and Add sub jobs to a project.
Limitations:
For customers using the Company level ERP Integrations tool
The default segments in WBS are compatible with Procore's ERP Integrations tool. However, some integrations do NOT yet support custom segments.For customers who have independently developed or purchased a third-party solution to integrate with Procore
To take advantage of the custom segment capabilities associated with WBS, any existing API integrations that you have independently developed or purchased to interact with Procore must be updated to support Procore's new WBS API.
Prerequisites
Do you want to copy the WBS from an existing project to your new project? If so, a Procore user who meets the required user permissions will need to configure the source project as a project template. A source project is the project that contains the WBS you want to copy to your new one. For instructions see, Configure a project template. One that step is complete, you'll be able to select the 'Copy the WBS from another project' option detailed in the steps below.