Set project working days
Things to Consider
Required User Permissions:
'Admin' level permissions on the Project level Admin tool.
Additional Information:
Days not selected as working days will be ignored when calculating due date.
The project's working days will affect the due date of item in the following tools:
Action Plans
Correspondence
Custom Tools
Observations
Snag List
RFIs
RFQs created from change events
Submittals
Tasks
Steps
Navigate to the Project level Admin tool.
Under 'Project settings', click Working days.
Mark the tickbox next to each day that will be included in the project's working days.
Note: Your changes will be saved automatically.