Add Budget production quantity to a project's budget

Background

A production quantity is a measurable amount of work on a construction project. For example, cubic yard of concrete, number of light fixtures or linear feet of piping. In Procore, Budget production quantity are the measurable amount a team expects to install on a project. Installed production quantity refer to the actual amount a team installs on a project.

Things to Consider

  • Required User Permissions:

    • 'Admin' level permission on the project's Budget tool.

  • Limitations:

  • Additional Information:

    • For companies using Procore's Field Productivity tools, you can use the Project level admin tool to import your Budget quantities instead of the steps below. See Import a unit quantity based Budget.

Prerequisites

Steps

  1. Navigate to the project's Budget tool.

  2. Click the Production quantities tab.

  3. Click Add line.

  4. Under Budget production quantity, do the following:

    • Cost code
      Enter the cost code that corresponds to the Budget production quantity for that cost code. These entries should exactly match the cost codes in your Procore project. If you enter a cost code that doesn't exist, the import will fail. Cost codes can be added as segment items in Procore's work breakdown structure.

    • Quantity
      Enter the budget quantity for that cost code using whole numbers.

    • UoM
      Select a Unit of Measure (UoM) from the drop-down list. To learn about the default selections in this list, see Which units of measure are included in Procore's master list? and Add a unit of measure to the unit of measure master list.

       Note

      You cannot add line item for Budget production quantity with UoMs in the 'Time' category in the Production quantity tab.

  5. Click Save.