Enable labour productivity

  1. Navigate to the project's Admin tool.

  2. Click the General tab under Project settings.

  3. Scroll to Advanced.

  4. Mark the Labour Productivity for Budget, change events and variations tickbox.

    Admin Advanced Enable Labor Productivity

  5. Click Update.