Add budget production quantity

  1. Navigate to the project's Budget tool.

  2. Click the Production quantities tab.

  3. Click Add line.

  4. Under Budget production quantity, do the following:

    • Cost code. Enter the cost code that corresponds to the Budget production quantity for that cost code. These entries should exactly match the cost codes in your Procore project. If you enter a cost code that doesn't exist, the import will fail. Cost codes can be added as segment items in Procore's work breakdown structure.

    • Quantity. Enter the Budget quantity for that cost code using whole numbers.

    • UoM. Select a Unit of Measure (UoM) from the drop-down list. To learn about the default selections in this list, see Which units of measure are included in Procore's master list? and Add a unit of measure to the unit of measure master list.

       Note

      You cannot add line item for Budget production quantity with UoMs in the 'Time' category in the Production quantity tab.

  5. Click Save.