Create a commitment variation from a change event

Background

In Procore, a is any change that affects the scope of a construction project. Once a change event is recorded in Procore, project teams have the option to create a request for quote to obtain quotes from the responsible contractors. See Create RFQs from a change event.

You can create a commitment variation from a change event either before or after the associated RFQ has been responded to or reviewed. However, if you wait until after the RFQ has been reviewed and the RFQ status is set to 'Pending Final Approval,' the variation's Bill of Quantities (BOQ) automatically populates with the amounts from the RFQ during the variation creation process. For more information about RFQ statuses, see What are the different RFQ statuses and how do they affect cost and variation amounts?

The process you use when managing changes in Procore also depends upon how your project's commitment variation tiers are configured. To learn more, see What are the different variation tier setting in Project Financials?

Things to Consider

  • Required User Permissions:

    • 'admin' level permission on the project's commitment tool.

    • 'Standard' level permissions on the project's Commitments tool and added to the 'Private' drop-down list and the 'Allow standard level users to create CVs' configuration must be selected.

Steps

  1. Navigate to the project's change event tool.

  2. Select one or more change event line item you want to include in the variation.
    Note: You can select line item across multiple change event. You can also use the Filter drop-down to filter by vendor.

  3. Click the Add to button.

  4. Hover over Commitment VAR then click New commitment VAR.
    Note: The line items on the variation's BOQ are created from line items on the change event.

  5. Select the destination contract using one of the following options:

    • Contracts with matching cost codes: Select a contract that shares matching cost codes with the selected change event line items.

    • Contracts: Select from any active commitment contract on the project.

  6. Complete the following information:

    • Number
      This field automatically populates based on the number of variations already created. By default, the number will automatically increment by one.

       Tip

      How does Procore assign numbers to commitment variations? To learn more, see Can I customise the numbering system for financial objects in Procore?

    • Revision
      This field displays the variation's revision number. When a variation is first created, its revision number is zero. A variation could have multiple revisions because of feedback from a reviewer/approver. This field must be manually entered as revisions are not automatically tracked.

    • Title
      This field will automatically populate with the name of the change event.

    • Status
      Select the current state of the variation. Procore's default status is Pending-In Review.

      Note to user with the claimable variations feature enabled.

      Procore's new Pending - billable status allows you to payment application an amount immediately while the variation remains unapproved. This status automatically makes the bill of quantities (BOQ) editable and is exclusively available for single-tier variations on commitments and main contracts. See Update the tool settings for contracts & variations.

    • Private
      Tick this box so only you and users with 'admin' level access on variations can view this variation.

    • Change reason
      The change reason field will populate with the change reason you selected in the change event; however, you can edit as necessary. Select the reason for the potential variation, either client request, design development, allowance, existing condition, contra charge or any options customised by the Procore administrator. Set the default change management configurations.

    • Accounting method
      This field inherits the accounting method that was specified in the commitment (e.g. Amount based).

    • Due date
      Enter the date the variation is due.

    • Payment application date
      Enter the date the variation was payment application.

    • Paid date
      Enter the date the variation was paid.

    • Designated reviewer
      Select a user to review the variation.

    • Request received from
      Select a user from the project's Directory who you are submitting the potential variation on behalf of.

    • DescriptionEnter a more detailed description of the variation.

    • Programme impact
      If known, you can provide an estimate of the number of additional days that would potentially be added to the current Project Programme if the variation were approved.

    • Location
      Use the location drop-down menu to select a location the [item] impact. Either select from the predefined locations or see How do I add a multi-tiered location to an item? This location may be as general as the site location at the first tier or as specific as where on the site the contractor will be working at the second tier.

    • Reference
      Reference any other tools, materials, drawings or documents that are related to the potential variation.

    • Executed
      Tick this box once the variation has been completed.

    • Field change
      Tick this box if the variation is a field change.

    • Paid in full
      Tick this box to indicate you have received payment for this change.

    • Change event line items
      If your project is integrated with enterprise resource planning:

      • Existing line item: Select an existing line item from the drop-down menu update its budget code to match the selected BOQ code and displays its existing tax code in read-only mode.

      • New line item: Select New line item if the budget code is brand new or not linked to an existing code. This creates a zero-pound (£0) line item in the commitment's bill of quantities (BOQ). You must select a value from the newly displayed tax code drop-down menu before creating the line item.

      If your project is not integrated with enterprise resource planning, you can skip this action and proceed to create the variation.

    • Attachment
      Attach any relevant documentation. Note: If there is an associated request for quote and the reviewer has attached any documentation to their RFQ response, the change events tool can be configured to add those attachments to new variations. See Configure advanced settings: Change events.

  7. Click Create. The Bill of Quantities for the variation will be created from the change event line items. You can click into the Bill of Quantities tab to verify your line items.

     Note

    Change event line items by default will pass the latest cost amount to the commitment variation bill of quantities line items.

    If a main contract variation was associated with that change event line item before the creation of the commitment variation, the change event line item will then pass the latest price amount to the commitment variation Bill of Quantities line item.