Create a commitment variation from a change event
Background
In Procore, a A change event is any event resulting in a modification that affects the scope of work on a construction project and the project’s programme and/or cost(s). In Procore, a change event can be recorded in the system and precedes the creation of a variation, which allows your team members and stakeholders to prepare for a cost change before it becomes an actual cost.
You can create a commitment variation from a change event either before or after the associated RFQ has been responded to or reviewed. However, if you wait until after the RFQ has been reviewed and the RFQ status is set to 'Pending Final Approval,' the variation's Bill of Quantities (BOQ) automatically populates with the amounts from the RFQ during the variation creation process. For more information about RFQ statuses, see What are the different RFQ statuses and how do they affect cost and variation amounts?
The process you use when managing changes in Procore also depends upon how your project's commitment variation tiers are configured. To learn more, see What are the different variation tier setting in Project Financials?
If your project is using the one (1) tier variation configuration, you will only need to create a CV. See Create a commitment variation. Note: If you are using the DocuSign integration, please see Complete a commitment variation with DocuSign® instead.
If your project is using the two (2) tier variation configuration, first you will Create a commitment potential variation from a change event. Next, you will create a CV from the Commitments tool. See Create a commitment variation.
Things to Consider
Required User Permissions:
'admin' level permission on the project's commitment tool.
'Standard' level permissions on the project's Commitments tool and added to the 'Private' drop-down list and the 'Allow standard level users to create CVs' configuration must be selected.
Steps
Navigate to the project's change event tool.
Select one or more change event line item you want to include in the variation.
Note: You can select line item across multiple change event. You can also use the Filter drop-down to filter by vendor.Click the Add to button.
Hover over Commitment VAR then click New commitment VAR.
Note: The line items on the variation's BOQ are created from line items on the change event.Select the destination contract using one of the following options:
Contracts with matching cost codes: Select a contract that shares matching cost codes with the selected change event line items.
Contracts: Select from any active commitment contract on the project.
Complete the following information:
Number
This field automatically populates based on the number of variations already created. By default, the number will automatically increment by one.TipHow does Procore assign numbers to commitment variations? To learn more, see Can I customise the numbering system for financial objects in Procore?
Revision
This field displays the variation's revision number. When a variation is first created, its revision number is zero. A variation could have multiple revisions because of feedback from a reviewer/approver. This field must be manually entered as revisions are not automatically tracked.
Title
This field will automatically populate with the name of the change event.
Status
Select the current state of the variation. Procore's default status is Pending-In Review.
Procore's new Pending - billable status allows you to payment application an amount immediately while the variation remains unapproved. This status automatically makes the bill of quantities (BOQ) editable and is exclusively available for single-tier variations on commitments and main contracts. See Update the tool settings for contracts & variations.