Create a potential variation for a client contract from a change event

Background

If your company has enabled the change event tool and configured your project to use a two (2) tier variation structure, the change event process requires you to create a potential variation. Then, you will create the client contract variation from the client contract tool. For details about the tiers, see What are the different variation tier settings in Project Financials?
Note: Procore recommends that you create a potential variation only for change event items that are Out of scope and must be submitted to the client/owner for approval.

When you create a potential variation, the Bill of Quantities (BOQ) will populate with the revenue ROM values. If you have the revenue ROM functionality hidden, the value will depend on the scope of the change event. For in scope or TBD scope change event, the PV will populate with £0. For Out of scope change events, the PV will populate from the RFQ if the status of that RFQ is Pending final approval. If there is no RFQ with that status, it will populate from the cost ROM. For more information about RFQ statuses, see What are the different RFQ statuses and how do they affect cost and variation amounts?.

Things to Consider

  • Required User Permissions:

    • 'Standard' level permission or higher on the project's change event tool.
      AND

    • 'Standard' level permissions on the project's client contracts tool and the 'Allow standard level users to create PVs' configuration setting must be enabled on the client contracts tool.

  • Additional Information:

    • Depending on the variation tier configuration setting configured for the client contract tool, potential variations can be transitioned into one (1) of the following items:* For two (2) tier variations, a .* For three (3) tier variations, a .* To learn more see, What are the different variation tier settings in Project Financials?

Prerequisites

  • The change event tool must be turned ON on the project. See Add and remove project tools.

  • The two (2) tier variation configuration setting must be turned ON the client contract tool.

  • The project's client contract must be in the 'Approved' status.

Steps

  1. Navigate to the project's change event tool.

  2. In the table, mark the tickboxes for one (1) or more change event line item(s) to include in the new potential variation.

     Note

    Procore creates the potential variation's Bill of Quantities (BOQ) using the selected change event line item(s).

  3. Click the bulk actions menu and choose the Create client PV option. Then choose the appropriate contract option from the sub menu.

  4. In the 'New potential variation' page, complete the following data entry:

    •  Tip

      How do you collect signatures with DocuSign? After the data entry for the item is complete, Procore recommends changing the item's status to 'Out for Signature' before clicking the Complete with DocuSign button to launch the DocuSign® application. If you have not previously signed in, you will be prompted to Log in to DocuSign®. Once you are signed in, you can prepare the DocuSign_®_ envelope for signatures. After the signature process is complete, Procore automatically changes the status of the item to 'Approved' and marks the item as 'Executed'. To learn more, see DocuSign®.

    •  Notes
      • Procore automatically assigns the item a new number in sequential order. For example; 001, 002, 003 and so on.

      • To use a custom numbering scheme, enter any set of alphanumeric characters. Procore automatically assigns new numbers in sequential order using your custom scheme.

    •  Note

      If the request for quote feature is turned ON, you can configure the change events tool to include any attachments added to a reviewer's RFQ response. For instructions, see Configure settings: Change events.

  5. Click Create.

     Notes
    • The Associated line item drop-down list only appears if your company's Procore account is integrated with an integrated ERP system and the main contract tool is active on the project.

    • When adding line items to the variation's bill of quantities, you must select an associated line item for each new line item. You can designate one (1) associated line item or use the same associated line item for multiple line items.