Create a potential variation for a client contract from a change event
Background
If your company has enabled the change event tool and configured your project to use a two (2) tier variation structure, the change event process requires you to create a potential variation. Then, you will create the client contract variation from the client contract tool. For details about the tiers, see What are the different variation tier settings in Project Financials?
Note: Procore recommends that you create a potential variation only for change event items that are Out of scope and must be submitted to the client/owner for approval.
When you create a potential variation, the Bill of Quantities (BOQ) will populate with the revenue ROM values. If you have the revenue ROM functionality hidden, the value will depend on the scope of the change event. For in scope or TBD scope change event, the PV will populate with £0. For Out of scope change events, the PV will populate from the RFQ if the status of that RFQ is Pending final approval. If there is no RFQ with that status, it will populate from the cost ROM. For more information about RFQ statuses, see What are the different RFQ statuses and how do they affect cost and variation amounts?.
Things to Consider
Required User Permissions:
'Standard' level permission or higher on the project's change event tool.
AND'Standard' level permissions on the project's client contracts tool and the 'Allow standard level users to create PVs' configuration setting must be enabled on the client contracts tool.
Additional Information:
Depending on the variation tier configuration setting configured for the client contract tool, potential variations can be transitioned into one (1) of the following items:* For two (2) tier variations, a
.* For three (3) tier variations, aIn Procore, a client contract variation (CCV) is a variation that affects a client contract. A two-tier variation setup typically consists of a bundle of potential variations (PVs) that must be approved by the main contractor or client. A three-tier variation setup typically consists of a bundle of variation requests (VRs) that must be approved by the main contractor or client.
.* To learn more see, What are the different variation tier settings in Project Financials?A variation request (VR) is a Procore-specific package that can be created to contain one (1) or more potential variations (PVs). A VR is a formal request sent to a project’s owner that groups multiple PVs for a single scope of work into a single package for review and approval.
Prerequisites
The change event tool must be turned ON on the project. See Add and remove project tools.
The two (2) tier variation configuration setting must be turned ON the client contract tool.
The project's client contract must be in the 'Approved' status.
Steps
Navigate to the project's change event tool.
In the table, mark the tickboxes for one (1) or more change event line item(s) to include in the new potential variation.
NoteProcore creates the potential variation's Bill of Quantities (BOQ) using the selected change event line item(s).
Click the bulk actions menu and choose the Create client PV option. Then choose the appropriate contract option from the sub menu.
In the 'New potential variation' page, complete the following data entry:
Sign with DocuSign®If you have enabled the Procore + DocuSign® integration (see Enable or disable the DocuSign® integration on a Procore project), a tick appears in this box by default. If you do NOT want to collect signatures with DocuSign®, remove the mark.
TipHow do you collect signatures with DocuSign? After the data entry for the item is complete, Procore recommends changing the item's status to 'Out for Signature' before clicking the Complete with DocuSign button to launch the DocuSign® application. If you have not previously signed in, you will be prompted to Log in to DocuSign®. Once you are signed in, you can prepare the DocuSign_®_ envelope for signatures. After the signature process is complete, Procore automatically changes the status of the item to 'Approved' and marks the item as 'Executed'. To learn more, see DocuSign®.