Approve or reject commitment variations

Background

A commitment variation (CV) details a change in cost that affects the original commitment. When you create a variation, you can assign another project user as its 'designated reviewer'. You can only assign one (1) Procore user as a 'designated reviewer' per commitment. Before a reviewer can submit an 'Approve' or 'Reject' response, the variation must be in the Pending - In Review status.

Things to Consider

  • Required User Permissions:

    • To approve or reject a commitment variation, 'Standard' level permission or higher on the project's commitment and variation tool and added as the 'designated reviewer' on the variation.

       Tips
      • How do you assign a 'designated reviewer' to a variation? For instructions, see Create a commitment variation or Edit a variation.

      • How do you view a commitment variation that has been marked 'Private'? You must be granted 'Standard' level permission on the project's commitment tool and added as a member of the 'Private' drop-down list on the commitment. See Create a commitment.

  • Additional Information:

    • Only one (1) user can be assigned as the 'designated reviewer' on the variation.

    • The 'designated reviewer' must submit an Approve or Reject response in Procore.

    • The 'designated reviewer' cannot submit a response to the variation from the Procore email notification.

  • Limitations:

    • The 'designated reviewer' field is only available on downstream variations for a commitment. This fields is NOT available on an upstream potential variation.

Prerequisites

Steps

  1. Open the variation requiring your response. Here are ways for a 'designated reviewer' to find it:

    • Locate the email message with the subject line: 'FW: Commitment variation: Title.' Then the View online link in the email notification to view the variation in Procore.

       Notes

    • Navigate to the project's Home page and click the variation's link in the 'My open items' area. See About the project Home page.

    • Navigate to the project's Commitment tool. Locate the commitment contract in the table and click the Number link to open it. Then click the contract's Variations tab. Locate the variation and click View. See View variations.

    • Navigate to the project's Variations tool. In the Commitments tab, locate the variation and click View. See View variations.

  2. Review the variation.

  3. When you are ready to submit an 'Approve' or 'Reject' response, scroll to the Reviewer's response box.

  4. Choose from these options:

    Reviewer Response2015 05 04 12 02 23

    • To approve the variation, enter any approval comments. Then click Approve this CV.

       In Beta

      Note to users participating in the 'Subcontractor Estimated Completion' limited release beta programme. When a user places a variation in the 'Approved' status and it includes a value in 'programme impact' field of the variation, Procore automatically updates the 'estimated completion date' field in the commitment contract by the number of days entered.

    • To reject the variation, enter an explanation about the rejection. Then click Reject this CV.

 Notes

After approving or rejecting a variation, Procore does the following:

  • Sends an email notification about your response to the creator of the variation.

  • Automatically adds your name to the 'Reviewer' field on the variation to indicate that the 'Reviewer's Response' is complete.

  • Adds the date you submitted your response to the 'Review Date' field.