Configure advanced settings: Connection manager

Background

You can use the setting in the project's Connection Management tool to manage notifications for new project connections, disconnections and connection request activity (if review is required).

Things to Consider

Configure Settings

 

Steps

  1. Navigate to the project's Connection Manager tool.

  2. Click the Configure Settings Icons Settings Gear icon.

  3. Select who should receive notifications. See Who receives notifications about project connections?

    • All users with Connection Manager admin permissions
      Note: This only includes users in the project's Directory.

    • Specific users
      Note: You can remove users, as well as add users who have Procore administrator permissions that have not been added to this project's Directory.1. Enter and select the specific user's names.

  4. Click Update.

See Also

Loading related articles...