Create and manage Site Diary segments (Android)

Background

You can create and manage multiple Site Diaries (segments) within the same project on the same day. The log segments help you organise diary entries by location, phase, crew, shift or company — so documentation reflects how work is actually performed on site. Each segment support its own independent diary entry for accurate, relevant data capture.

Project teams can filter log views by segment to focus on the logs most relevant to them. For example, site managers can focus on their assigned segments without distraction from other parts of the project. The log segments are also compatible with 360 Reporting for aggregated, Project level analysis.

The log segmentation helps project team to:

  • Structure logs in ways that accurately mirror the work being performed - by crew, area or phase.

  • Use the tool more effectively for clearer attribution of work and Ownership, smoother collaboration and simpler data review and approvals.

  • Prepare high-quality project documentation for a larger project or complex reporting.

Note: PDF exports (include segment names, organised by segment ) and pagination (added to the segments setting section) capabilities are supported.

Things to Consider

Steps

  1. Open the Procore app on an Android mobile device and select a project.
    The Tools screen loads, displaying all tools available for this project.

  2. Tap the Site Diary tool.
    You can view the Site Diary screen displaying all segments for the project.

  3. Tap the date for which you want to create a new entry.

  4. Tap the Icon Arrow Expand icon next to the desired log type for which you want to add a segment. For example, manpower.
    You can view all segments for the selected log type.

  5. Tap the quick createIcon Plus Quick Create Mobile2icon.
    The create entry screen opens. For example, create manpower entry.

  6. Tap each field and enter appropriate information.
    For example, you can enter a name for the diary entry (North Tower - Office) in the Project segment field.

  7. Tap Create.
    The new log segment is created for the selected log type.

  8. To view the project segments, do the following:

    1. In the main Site Diary screen, tap the Filter option.
      The Project segments screen opens, providing options to choose All segments or the individual segments.
      Note: To view log segments in the the Calendar view, go to the Calendar view and choose a date.

    2. Select a project segment to view all activities.

    3. Tap Apply.