Import an estimate

Background

Using a predefined Excel template allows you to quickly add large amounts of estimate data into Procore at once. This process ensures that your data is formatted correctly for a seamless import, reducing manual entry errors and saving time during the estimating phase of a project.

Things to Consider

  • Required permissions:

    • 'Standard' or 'admin' level permissions on the project's Estimating tool.

  • Additional Information:

    • Do not modify the column headers in the predefined template, this will cause the import to fail.

    • To import an estimate, you must use the provided template.

Important!

Large estimate imports may fail or process slowly.

Steps

  1. Navigate to the project's Estimating tool.

  2. Click Import.

  3. Select Download estimate import template.

  4. Once downloaded, open the file in Microsoft Excel.

  5. Enter the estimate information into the predefined columns. Show / hide details

    • Group: Enter the group name. Use this to keep your tender organised so tenderers and reviewers can see cost broken down by specific project area.

    • Layer: Assign an internal layer to make the estimating line item visible in the Takeoff tab.

    • Part: The specific material, labour or Equipment item associated with a line item. The imported data is plain text information and is not pulled from the cost catalogue.

    • Part multiplier: Enter a whole number or decimal. A factor applied to a single part to account for repetitive usage.

    • Group multiplier: Enter a whole number or decimal at the group header level. A factor applied to an entire group of cost.

    • Subtotoal item cost: Enter the calculated total for that line item.

      • Quantity x unit cost

    • Unit labour time: Enter the estimated time it takes to install or perform one unit of work.

    • Unit of Measure (labour time): Enter the time increment used for labour (usually hours or minutes).

    • Difficulty factor: Enter a factor greater than 1.0 to increase the labour time. For example, enter 1.25 to add a 25% "difficulty" buffer to the labour units.

    • Quantity: Enter the total amount of the item required for the scope. Ensure the quantity aligns with the units defined in the Unit of Measure field.

    • Unit of Measure (quantity): Enter the Unit of Measure for the physical material.

    • Unit cost: Enter the base price of one unit of material or labour before any markups.

    • Waste: Enter a percentage to account for overall project scrap, breakage or minor errors across all resource types (Material, Labour, Equipment).

    • Material waste: Enter the specific loss factor expected for that material. Unlike the general 'Waste' field, this ensures your labour hours don't accidentally inflate just because you need to buy extra physical product.

    • Margin: Enter your target profit percentage.

      • Sales price (margins) = subtotal item cost ÷ (1 - margin %)

    • Labour margin: Enter your target profit percentage applied exclusively to the labour cost portion of a line item. This allows for granular control over your overhead recovery on manpower.

  6. Save your changes in the Excel file.

  7. In Procore, click Import.

  8. Select Estimate import template.

  9. Click Upload files.

  10. Select the CSV file you want to upload.

  11. Click Open.

  12. Once uploaded, click Attach.

    • Once successful, your estimate appears automatically in the Estimating tool.

    • If an error banner appears, review the details, correct the file and re-upload.