Background
After you have completed an estimate in the Estimating tool, you can use the 'Send to Budget' option to copy and import line items from that estimate into the project's Budget. The cost codes and amounts on the estimate will be reflected on the Budget.
Things to Consider
Your company must be licenced for Procore's Project Financials tools.
To send an estimate to the Budget, the estimate must be set as the primary estimate as indicated with a tick
icon.Default below the line adjustments such as profit, overhead, discount, taxes and others are set in the company's Admin tool.
If there is a part on the estimate with Labour, Materials and Tax applied to it, the item will appear as three (3) separate line items in your budget (one for labour, one for materials and one for tax).
Currently Send to Budget sends only data from the primary estimate without any included estimates.