Create a simplified payment application for a commitment
Background
Simplified Payment Applications is a purpose built payment applications experience for materials suppliers, consultants and service providers who bill more frequently than once per period. Unlike Construction Progress Payment Applications, Simplified Payment Applications allows you to edit any unapproved or unsynced payment application at any time and provides a streamlined Bill of Quantities (BOQ) view.
Things to Consider
Required User Permissions:
'Standard' or 'admin' level permissions on the project's commitment tool.
Additional Information:
Simplified Payment Applications must be enabled in the commitment tool's configuration setting prior to creating a payment application.
Steps
Navigate to the project's Commitments tool.
Click View next to the commitment you want to payment application.
Click the Payment applications tab.
Click Create.
In the General information section, enter the following:
Payment application #: Enter a unique identifier for the payment application.
Valuation period: Select the appropriate period.
Billing date: Select the date of the payment application.
In the Bill of quantities section, click Edit.
Enter the billing amounts in the following columns:
Work completed this period (£): Enter the pound amount for work performed during this period.
Work retention this period (£): Enter the amount of retention to hold for this period.
Total retention released: Enter any retention amounts you want to release to the vendor.
Review the Cumulative retention and Cumulative completed columns to verify the total amounts billed across the entire commitment.
Click Save.
This example illustrates how a materials supplier uses Simplified Payment Applications to bill for multiple deliveries within a single month. Unlike Construction Progress Payment Applications, Simplified Payment Applications allows the supplier to submit multiple payment applications without waiting for the next payment application to be approved and provides a clear view of cumulative billing against the total contract value.
Scenario
A project team awards a £10,000.00 purchase order to a concrete supplier. The contract is configured to use the simplified Payment Applications method with a 10% retention rate.
Payment application #1: Initial delivery
The supplier delivers the first load of materials and creates a payment application for £2,000.00.
Work completed this period (£): £2,000.00
Work retention this period (£): £200.00 (10% of the work completed)
Cumulative completed: £2,000.00
Cumulative retention: £200.00
Net amount due: £1,800.00
Payment application #2: Second delivery (same valuation period)
One week later, the supplier delivers more materials and creates a second payment application for £3,000.00. Because simplified Payment Applications is enabled, they do not need to wait for the first payment application to be approved or for a new valuation period to begin.
Work completed this period (£): £3,000.00
Work retention this period (£): £300.00
Cumulative completed: £5,000.00 (payment application 1 + payment application 2)
Cumulative retention: £500.00 (payment application 1 + payment application 2)
Net amount due: £2,700.00
Payment application #3: Correcting a previous entry
The supplier realises they overcharged on payment application #1. With Simplified Payment Applications, the Project Administrator can edit payment application #1 directly to change the amount to £1,500.00 without deleting payment application #2.
Validation check: Procore® automatically updates the Cumulative completed and Cumulative retention values across all payment applications to reflect the change.
New cumulative completed: 4,500.00(1,500.00 + £3,000.00)
Payment application #4: Final delivery and retention release
The supplier delivers the remaining materials (5,500.00)and requests the release of all held retention(450.00).
Work completed this period (£): £5,500.00
Total retention released: £450.00
Validation check: Procore® validates that the £450.00 release does not exceed the £450.00 currently held in cumulative retention.
Cumulative completed: £10,000.00 (Total contract value)
Cumulative retention: £0.00
Net amount due: 5,950.00(5,500.00 work + £450.00 released retention)