Compare Lookahead to master programme

Background

When you work in a Lookahead, you are managing a granular field plan that lives "on top" of the master programme. To ensure the site team stays aligned with the project's overall goals, Procore uses shadow bars. These allow you to see the original master programme dates behind your active field task, making it immediately obvious if your current plan is deviating from the master timeline.

Things to Consider

  • Colour logic:

    • Colourful bars: Represent your active field plan (the lookahead tasks).

    • Light Grey shadow bars: represent the dates currently set in the master programme.

  • Dynamic update: If the master programme is re-imported (Option 1) or edited, the grey shadow bars will shift automatically, while your colourful field bars remain in place for comparison.

Important
  • Update an existing programme: Re-importing completely overwrites and replaces the previously uploaded programme—it does not append or add to existing data. You can upload update files directly.

  • Uploading a programme with different task: If your new programme contains different/restructured task, you must Reset the Project Programme first to avoid task-matching errors.

Steps

Enable variance visibility

  1. Navigate to the Lookahead tab.

  2. Ensure you have "fetched" activities from the master programme.

  3. Look at the Gantt chart. Each activity will display two bars: the editable colourful bar and the light grey shadow bar underneath it.

Interpret the variance

Observe the alignment between the two bars:

  • Aligned: The site team is working exactly according to the master programme.

  • Colourful bar is to the right: The field plan is slipping (starting or finishing later than the master programme).

  • Colourful bar is to the left: The site team is ahead of programme (finishing earlier than the master programme).

  • Extended bar: If the colourful bar is longer than the shadow bar, the task duration in the field is taking longer than originally estimated.

Analyse deadline variance (optional)

If you have set hard deadlines on your activities:

  1. Locate the Deadline variance column in the grid.

  2. A positive number indicates the number of days the current finish date has slipped past the locked deadline.

  3. Use the Filter icon on this column to show values "Greater than 0" to quickly see all late task.