Compare Lookahead to Master Schedule
Background
When you work in a Lookahead, you are managing a granular field plan that lives "on top" of the master schedule. To ensure the field team stays aligned with the project's overall goals, Procore uses Shadow Bars. These allow you to see the original master schedule dates behind your active field tasks, making it immediately obvious if your current plan is deviating from the master timeline.
Things to Consider
Color Logic:
Colorful Bars: Represent your active field plan (the lookahead tasks).
Light Gray Shadow Bars: Represent the dates currently set in the Master Schedule.
Dynamic Updates: If the Master Schedule is re-imported (Option 1) or edited, the gray shadow bars will shift automatically, while your colorful field bars remain in place for comparison.
Updating Existing Schedules
When updating an existing schedule file in your third-party scheduling software (e.g., Microsoft Project, Primavera P6, Phoenix):
Always use Save to update your file. This preserves the internal activity IDs needed to map existing Lookahead activities in Procore.
Do not use Save As. Using Save As creates a brand new schedule file with new internal IDs. Attempting to upload a Save As copy into Procore will trigger an error because it breaks the associations with your project's Lookahead activities.