Compare Lookahead to master programme
Background
When you work in a Lookahead, you are managing a granular field plan that lives "on top" of the master programme. To ensure the site team stays aligned with the project's overall goals, Procore uses shadow bars. These allow you to see the original master programme dates behind your active field task, making it immediately obvious if your current plan is deviating from the master timeline.
Things to Consider
Colour logic:
Colourful bars: Represent your active field plan (the lookahead tasks).
Light Grey shadow bars: represent the dates currently set in the master programme.
Dynamic update: If the master programme is re-imported (Option 1) or edited, the grey shadow bars will shift automatically, while your colourful field bars remain in place for comparison.
Update an existing programme: Re-importing completely overwrites and replaces the previously uploaded programme—it does not append or add to existing data. You can upload update files directly.
Uploading a programme with different task: If your new programme contains different/restructured task, you must Reset the Project Programme first to avoid task-matching errors.