Add quantities to a timesheet (Android)

Background

Production quantities are a measurable amount of work on a construction project. For example, cubic yards of concrete, number of light fixtures or linear feet of piping. In Procore, there are two types of production quantity:

  • Budget production quantity refers to the measurable amount a team plans to install on a project.

  • Installed production quantity refers to the actual amount installed on a project by a point in time.

After installed production quantity have been entered in a timesheet, they can be tracked against the imported Budget production quantity using the Production quantity report.

Things to Consider

Prerequisites

Steps

After you create your timesheet, perform the following actions:

  1. Tap Submit.

  2. Under 'Select an option', Submit and add quantity.
    Submit And Add Quantities

  3. Tap Add quantity.

  4. Tap Add units.

  5. In the Units installed today field, enter the number of item installed for the day.

  6. Optional: Enter any notes.

  7. Tap Apply to save your changes.