Set Up the Procore Labour Productivity Cost Budget View

Background

The 'Procore labour productivity cost' budget view provides project teams with the ability to include production quantities on the project's Budget. See What are 'production quantities'? Building off the real-time labour costing feature, the 'Procore labour productivity cost' budget view is designed to provide self-performing and specialty contractors with the ability to gain greater insight into your project's production rate to make better decisions that maximise profit margins. With this release, you can:

  • Add and import production units to a project's budget in Procore's Financial Management tools: Budget, change events and variations.

  • Collect production units from site personnel with timecard entries in the Site Diary and both the Timecards and Timesheets tools.

  • Track and compare Budget production units to installed production units using Procore's Budget and report tools.

By default, Procore provides its users with a standard 'Procore labour productivity cost' budget view, which is available to your company's Procore administrator in the Company level Admin tool.

Example

Procore labour productivity cost budget view in the Budget tool

The illustration below shows you the recommended layout for the 'Procore labour productivity cost' budget view, as it will look when applied to your project's Budget tool.

Budget Procore Labor Prod Cost View

Things to Consider

Prerequisites

  • Verify that the Timesheets tool is active in your company's Procore account.
    Note: To do this, navigate to the Company Admin tool. Under company settings, click Account information. Under Resource management, verify that Timesheets is 'licence'.

  • Assign the default cost type for timecard entries in the Company level Timesheets tool. See Configure settings: Company level Timesheets.

  • Add the following tools to the Project tools menu. See Add and remove project tools.

    • Direct Costs

    • Main Contracts

    • Optional : Timecard

    • Timesheets

    • Budget

Steps

  • Step 1: Create a new budget view

  • Step 2: Optional: Custom the budget view

  • Step 3: Preview the budget view

  • Step 4: Assign the budget view to a Procore project

Step 1: Create a new budget view

  1. Navigate to the Company Admin tool.

  2. Under Tool settings, click Budget.

  3. Click Set up new budget view.
    Set Up New Budget View

  4. Under standard views, highlight Procore labour productivity cost.
    Procore Labor Productivity Cost View

  5. Click Create.

  6. Name your view as follows:

    • View name. Enter a name for your new view. In this example, we named it: labour productivity cost

    • View description. Enter a description for your view. In this example, we entered: Recommended view for labour cost Productivity report

  7. Click Configure columns.
    This opens the Configure columns window pictured below. From this point, continue with Step 2: (Optional) customise the budget view.

Step 2: Optional: Customise the budget view

If you want to customise the Procore labour productivity cost budget view, you can click the Configure columns button. This opens the Configure columns window, which allows you to edit the budget view. To learn about your editing options, see Configure the columns for a budget view in the Set up a new budget view tutorial. When you are finished, click the 'x' in the Configure columns window to close it.

Step 3: Preview the budget view

After closing the Configure columns window, the system returns you to the new budget view's window. Under Column configuration, you can get an idea of how your budget view will look in Procore by selecting a project from the Preview with project drop-down list.

Step 4: Assign the budget view to a Procore project

  1. In the 'Procore labour productivity cost' view window, place ticks next to project boxes of your choice in the Assign to projects list.

    Assign To Projects

    • To assign the budget view to all of your company's Procore projects, place a tick in the All projects selected box.
      Notes:* For companies using the enterprise resource planning integration tool, you will see the 'All project using enterprise resource planning direct costs' tickbox.* You may also see the 'All projects using Procore direct costs' tickbox. However, it only appears when the direct cost tool is enabled on the project.

    • To assign the budget view to one (1) or more projects, place a tick next to the desired projects.
      Note: Select project templates to carry over the budget view to new projects created using those templates. See Carry over budget view from a project template.

  2. Click Done.

 Tip

After completing all of the above steps, you can provide your project team with instructions for applying the budget view to their project Budget. For details, see Apply the view, Snapshot, group and filter options on a budget view.