Things to know

Background

Each of Procore's available ERP connectors perform the basic function of syncing data between the ERP system and Procore, usually in the same way as other connectors. However, each connector has a unique set of items it can sync and the way those items are synced will vary based on how that ERP system and its corresponding integration are built to function.

Trimble® Spectrum, like all ERP integrations, has some key considerations, limitations and things to know about how each Procore object is synced. Those considerations, limitations and things to know are outlined in the table below according to tool or item being synced.

Things to know about the Trimble® Spectrum Connector

Procore item or setting

Considerations, limitations and requirements

Configuration settings & sync programme

  • Limitations

    • The integration is limited to (1) Procore Trimble® Spectrum company file per (1) Procore site. (A separate Procore Trimble® Spectrum company file for each project is NOT supported.)

    • This integration does NOT support the following items:

      • Commitment imports. You cannot import commitments from Trimble® Spectrum into Procore.

      • Multiple standard cost code lists. Although Trimble® Spectrum support multiple standard cost code lists, the integration by Procore requires you to choose one (1) Trimble® Spectrum cost code list per integration.

      • Sub jobs. The sub job feature is NOT supported with this integration. Sub jobs are always disabled in Procore projects that integrate with Trimble® Spectrum. While both Jobs and Master Jobs can be imported into Procore, each must run as a separate and unique project in Procore.

      • Multiple viewpoint® Spectrum® company. For each Procore company account, the integration is designed to support one (1) Trimble® Spectrum company.

      • Viewpoint® Spectrum® purchase order module. While you can create purchase orders in Procore, purchase orders are exported to Trimble® Spectrum as subcontracts. Procore purchase orders do NOT integrate with the Trimble® Spectrum purchase order module.

  • Data from these Procore tools and item do NOT sync with Procore viewpoint Spectrum®:

    • Commitment payment applications and payments

    • Trimble® Spectrum Main contracts.
      Note: You can sync main contract variations (MCVs) from Procore to Trimble® Spectrum. However, you cannot sync variations from Trimble® Spectrum to Procore.

    • Main contract payment applications and payments

    • Timecards/timesheets

  • Additional configuration settings

    • Direct export feature is available if users want to bypass the 'Send to ERP' step and accounting approver review for commitments, commitment variations and subcontractor payment applications.

    • In the ERP Integrations tool's Configure settings area, under 'Connection settings' you can update the following Trimble® Spectrum settings:

      • Service URL. Enter the URL for the Trimble® Spectrum microservice.

      • Service user. Enter the user name for the Trimble® Spectrum microservice.

      • Edit credentials. Click this link to reveal the service password box. Enter the new password for your Trimble® Spectrum microservice account here or click Cancel to keep the current password.

      • Status. Shows the current status of the service connection. The statuses are 'Connected' and 'Not connected.'

  • Additional information

    • Connect Trimble® Spectrum vendor records to Procore company records in the Directory tool.

    • Import new Trimble® Spectrum jobs to create Procore projects.

    • Sync Trimble® Spectrum project phases and cost types to Procore.

    • Export commitments (i.e., purchase orders and subcontracts) created in Procore's Commitments tool to create subcontracts in Trimble® Spectrum.

    • Sync Trimble® Spectrum Original Estimate/Budget with Procore.

    • Sync Trimble® Spectrum job costing information to Procore.

    • Import one (1) Trimble® Spectrum main contract to one (1) Procore project.

    • Export main contract variations (MCVs) to Trimble® Spectrum.

  • IMPORTABLE DATA: The automatic background sync programme is configurable in the enterprise resource planning integration tool setting. Never, Daily, Every 4 hours, Every 2 hours or hourly to stage Procore Trimble® Spectrum importable data (standard cost codes, project cost codes and cost types, jobs, budgets, main contracts, vendors and cost).

    • On demand syncs may also be initiated within the Procore ERP Integrations tool for importable standard cost codes and cost types, project cost codes and cost types, jobs, vendors and job costs.

  • EXPORTABLE DATA: All exportable information (Jobs, vendors, budgets, commitments, commitment variations and main contract variations) must be approved/accepted by an accounting approver, who are the only users that may initiate the export from Procore to Procore Trimble® Spectrum.

Work breakdown structure (WBS)

  • Considerations

    • When the Procore Trimble® Spectrum integration is configured, a new Company level cost code list will be generated for use with the integration called "Spectrum Standard Cost Codes".

      • When the connector is activated, Procore will sync phases from your Spectrum|Job cost|Phase Category code into the Procore Standard Phases list "Spectrum Standard cost codes".

      • Projects in Procore must be associated with the Spectrum Standard cost code list in order to be exported to Trimble® Spectrum.

      • Jobs that are imported from Trimble® Spectrum will automatically be associated with the Spectrum standard cost codes list.

  • Limitations

    • Sub jobs are NOT supported.

    • Custom WBS segments are NOT supported.

Companies

  • Import companies to Procore

    • You can filter companies that are ready for import by company type using the Type filter under the Companies tab on the ERP Integrations page.
      Note: You can filter companies by type, even those without a company type, to be synced to Procore.

  • Considerations

    • Companies in the Procore Directory can be synced with vendors in Procore Trimble® Spectrum in (3) different ways:

      • Procore Trimble® Spectrum vendors can be imported to Procore to create a new company in the Procore Directory.

      • Procore Trimble® Spectrum vendors can be linked to an existing company in the Procore Directory during import.

      • Companies in the Procore Directory can be exported to Procore Trimble® Spectrum to create a new vendor in Procore Trimble® Spectrum.


  • Additional
    information

    • There is a setting that can be enabled to allow adjustments made to the vendor (name, address, phone and fax numbers) in Procore Trimble® Spectrum to automatically update the associated synced company information in the Procore Directory during the next vendor refresh. The setting may be disabled if preferred.

      • Changes made to a company in Procore will NOT update the synced vendor in Procore Trimble® Spectrum.

    • The company in the Procore Directory must be synced with a Procore Trimble® Spectrum vendor before a commitment associated with that company in Procore may be exported to Procore Trimble® Spectrum.

  • Limitations

    • Companies in the Procore Directory can not be exported to Procore Trimble® Spectrum as AR customers.

    • Linking an existing Procore company with an existing Procore Trimble® Spectrum vendor can not be completed by exporting the company to Procore Trimble® Spectrum. Linking the (2) existing records together must be done via the Ready to import filter, using the Link to existing company/Show suggested Procore matches options.

Projects

  • Considerations

    • Projects that are in-progress or created before connection of the integration cannot be synced. Professional services for assistance with integrating in-progress/pre-existing project records are available for an additional fee.

  • Prerequisites

    • You must have a template job set up in Trimble® Spectrum. The template job supplies the division, cost centre, customer, taxable flag and price method code for the Procore project that is exported to Trimble® Spectrum.

  • Project export requirements

    • All cost code must have at least one (1) cost type assignment before the Procore project can be exported to create a new Job in Trimble® Spectrum.

    • If your cost code already have cost type assignments, your company has already configured the cost type assignments for your cost code.

    • When entering your project data, be aware of the following requirements:

      • Project name. Enter a name for the construction project. When the enterprise resource planning integration tool is enabled for Trimble® Spectrum, the project name is limited to a maximum of twenty five (25) characters in length.

  • Additional information

    • Any Project level cost codes that are not synced will automatically sync with your ERP when exporting your budget.

    • Before you can sync data project data between the two (2) systems, your Procore point of contact must enable the 'Can push to accounting' privilege for your company's accounting approvers. This gives users with 'Standard' level permissions to the ERP Integrations tool permission to accept or reject the data that is synced between Procore and Trimble® Spectrum.

Budget

  • Prerequisites for export from Procore

    • Add the Trimble® Spectrum job to Procore.

    • Create the project budget

    • The Budget must be locked in order to send to enterprise resource planning.

    • All the project's cost code and cost types have been synced with Trimble® Spectrum.

    • You must assign a cost type to each project cost code to export your budget, regardless of whether the cost code is included in the budget.

  • Syncing:

    • You can export budgets containing original line items with £0 values from Procore to Trimble® Spectrum.

  • Restrictions
    After exporting a Procore budget to Trimble® Spectrum, the following restrictions are in place:

    • You will no longer be permitted to import Trimble® Spectrum Budget into Procore.

    • The ability to unlock the Procore Budget, resend data to Trimble® Spectrum, add budget line items and create budget modifications will be disabled until the export from Procore to Trimble® Spectrum is complete.

  • Limitations

    • The Procore + Trimble® Spectrum does NOT sync 'Unit of Measure (UoM)' and 'unit quantity' values between systems. Currently, the Budget sync is amount-based only. This means you must manually enter the units in both Procore and in Trimble® Spectrum.

Budget Changes

  • Prerequisites

    • The budget must be synced and also locked.

  • Additional information

    • Budget changes only sync from Procore to Trimble® Spectrum.

    • Budget change will create a change request in Trimble® Spectrum.

Commitments

  • Prerequisites Before you can send a commitment to the enterprise resource planning integration tool, it must satisfy these prerequisites:

    • Contract company. Must be linked to a synced Trimble® Spectrum vendor.

    • Status. The status must be set to 'Approved' or 'Complete.'

    • Bill of Quantities (BOQ). Must include at least one (1) line item and all line items must contain Trimble® Spectrum cost code. All Bill of Quantities (BOQ) line items must be tied to the same cost type.

  • Additional information

    • If desired, you can configure your ERP integration default settings to use your Procore commitment number as the Trimble® Spectrum commitment ID during exporting. If enabled, the Trimble® Spectrum ID will auto-populate with the Procore contract number; however, the value can still be edited
      Note: Enabling this setting requires 'admin' level permission on the ERP integration tool.

  • Limitations

    • To sync a commitment, all bill of quantities (BOQ) line items must be tied to a cost code and category from your ERP-synced lists of standard cost codes and cost types.

    • Commitment synced to Trimble® Spectrum will NOT contain details regarding tax code.

    • After the commitments on a project have been synced with a company's Trimble® Spectrum system, Procore automatically restricts your ability to edit synced fields on a commitment. This is to ensure that the data remains in sync on both systems. The following fields cannot be edited after the commitment has been synced :

      • Contract company

      • Status

      • Bill of Quantities (BOQ) subtab (all fields)

    • If you need to delete a commitment after its been synced with your Trimble® Spectrum, you must first disconnect the link that exists between the two records in each system.

    • Once deleted, the commitment's data is permanently removed from Procore and cannot be retrieved.

Commitment variation

  • Minimum requirements
    In order to send a CV to enterprise resource planning, the CV must satisfy these requirements:

    • Contract company. Must be linked to a Trimble® Spectrum vendor.

    • Status. Must be 'Approved.'

    • Bill of Quantities (BOQ). Must include at least one (1) line item with a Trimble® Spectrum cost code. All Bill of Quantities (BOQ) line items must be tied to the same cost type.

  • Additional information

    • During exporting, you are prompted to fill in the Trimble® Spectrum change request ID. Commitment variations export to Trimble® Spectrum and create a change request ID.

    • If desired, you can configure your ERP integration default setting to use your Procore commitment variation number as the Trimble® Spectrum change request ID during exporting. If enabled, the Trimble® Spectrum change request ID will auto-populate with the Procore commitment variation number, however, the value can still be edited
      Note: Enabling this setting requires 'admin' level permission on the ERP integration tool.

  • Limitations

    • Procore does not permit users to delete synced commitments, so you must first unlink the records in the two systems to allow for deletion.

    • You cannot delete an 'Approved' variation. The status must be adjusted prior to deletion.

    • After a synced CV is unlinked and deleted, the data is permanently removed from the system and cannot be restored.

Main Contracts

  • Prerequisites
    The instructions below assume the following:

    • The Company level ERP Integrations tool has been configured to work with your company's Procore account.

    • The Trimble® Spectrum main contract that you want to sync with Procore has been updated. For example, you've added one or more BOQ line items to the contract in Trimble® Spectrum.

    • Within your ERP integration settings, ERP admins can enable the ability to designate your main contract as either Unit-based or Amount-based before importing to Procore.

  • Additional information
    The Re-import button is greyed out and unavailable when:

    • The prime contact has already been synced and there are no new un-synced line items.

  • Limitations

    • Unit pricing main contracts are not supported.

      • Contracts can be imported with unit-based lines to allow for manual input of units and quantity in the main contract tool upon import.

    • You should only import one (1) Trimble® Spectrum main contract to one (1) Procore project as having multiple synced main contracts will cause issues during MCV exporting.

      • MCVs will always export against the Primary Customer main contract.

Main contract variations (MCV)

  • Prerequisites

    • The company account must be integrated with Trimble® Spectrum.

    • The main contract tool must be an active tab on the project.

    • The MCV must be sent to the enterprise resource planning integration tool.

    • If any changes have been made to the main contract in Trimble® Spectrum, ensure that those changes are synced to Procore prior to creating and exporting your MCV.

    • Create or update the MCV in Procore.

    • Before you can send an MCV to the ERP integration tool, it must also satisfy these prerequisites:

      • Title. Must be 255 characters or less.

      • Status. Must be in the Approved status.

  • Syncing

  • Limitations

    • Unit pricing MCVs are not supported.

  • Additional information

    • During exporting, you are prompted to fill in the Trimble® Spectrum change request ID.

    • You can view the 'quantity', 'Unit of Measure (UoM)' and 'unit cost' fields without any values for line items in MCVs. Currently, these fields cannot be edited because the Procore + Trimble® Spectrum integration does not support this capability.

Job to date cost

  • Requirements

    • Enable the Project level Budget tool.

    • Must have the default enterprise resource planning budget view enabled to see cost sourced through the columns configured.

  • Additional information

    • The default Spectrum integration brings over cost as lump sum values against the budget code. Job cost transaction details is available as a custom integration add-on. Contact your Procore point of contact or customer success for more information.

Forecasting/projections

  • Requirements

    • Enable the Project level Budget tool.

    • The ability to export forecasting is enabled on a project by project basis within the projects budget setting.

  • Forecasting export will write the 'Estimated cost at completion' values from a Procore Budget to Trimble® Spectrum Projected cost.