Things to know

Background

Each of Procore's available ERP connectors perform the basic function of syncing data between the ERP system and Procore, usually in the same way as other connectors. However, each connector has a unique set of items it can sync and the way those items are synced will vary based on how that ERP system and its corresponding integration are built to function.

Yardi Voyager®, like all ERP integrations, has some key considerations, limitations and things to know about how each Procore object is synced. Those considerations, limitations and things to know are outlined in the table below according to tool or item being synced.

Things to know about the Yardi Voyager® Connector

Procore item or setting

Considerations, limitations and requirements

Configuration settings & sync programme

  • Sync programme for the following enterprise resource planning tabs runs daily 5am EST: cost codes, vendors, jobs.

  • All Yardi Voyager® jobs must be under the same entity.

  • The Direct Export feature is available if users want to bypass the 'Send to ERP' step and accounting approver review for commitments, commitment variations and subcontractor payment applications.

Cost codes/cost types

Add cost code to import to Procore

  • Required User Permission:

    • 'admin' level permissions on the project's admin tool

  • Prerequisites:

    • The enterprise resource planning integration tool must be enabled on your company's Procore account.

    • The project must be configured to use the Yardi Voyager® standard cost code list.

  • Supported cost code delimiters:

    • If your company has enabled the ERP Integrations tool for Yardi Voyager®, Procore permits the following cost code delimiters from Yardi Voyager®: hyphen/dash (-).

Projects

Important

  • Projects that are in-progress or created before connection of the integration cannot be synced. Professional services for assistance with integrating in-progress/pre-existing project records are available for an additional fee.

  • Add a Yardi Voyager® job to Procore

    • Job name/ID has a max character limit of 16.


  • Export a project from Procore to Yardi

    • Job name/ID has a max character limit of 16.

    • You must select the 'ERP standard cost codes' list for use on your new project.

    • All cost codes must have at least one (1) cost type assignment.

    • Procore project number must match Yardi Voyager® job code.

    • Procore WBS cost code/cost type list must match Yardi Voyager® cost code/cost types.


Copy over WBS sub job and cost code details when project templates are used

  • Requirements:

    • If you’re creating a Procore project with this setting enabled, ensure that all cost codes in the project template also exist in the Yardi Voyager® project before applying the template to the Procore project. For details on how to enable this setting, see Configure settings: Company level work breakdown structure.

Sub jobs

  • Syncing

  • Limitations

    • You can only view synced sub jobs under the 'Sub jobs' tab on the ERP integration page.

Project level work breakdown structure (WBS)

Budget

  • Additional Information:

    • You can export budgets with sub jobs on the Bill of Quantities (BOQ) line items.
      Note: You can export budgets with sub jobs only if you have imported the Yardi Voyager® Job as a sub job into Procore.

    • You can import original budget from Yardi Voyager®, but you cannot add multiple jobs to a single budget in Yardi Voyager®. To add sub jobs on a budget, you must export the budget from Procore.

Budget Changes

You can export budget changes with sub jobs on the Bill of Quantities (BOQ) line items.

Companies

Import companies to Procore

  • You can filter companies that are ready for import by company type using the Type filter under the Companies tab on the ERP Integrations page.
    Note: You can filter companies by type, even those without a company type, to be synced to Procore.


Adding a Yardi Voyager® vendor to the Procore Directory

  • Prerequisites:

    • Important! Before adding a vendor from Yardi Voyager® to Procore, always check to make sure that a matching vendor record does NOT already exist in Procore. If you do not perform this check, you might end up with duplicate or unlinked vendor/company entries.

  • Additional Information:

    • New company entries automatically inherit the appropriate Yardi Voyager® vendor ID.

  • Limitations:

    • Vendor ID has a max character limit of 12


Archiving a vendor in Procore

  • Additional Information:

    • You can only archive a vendor that is not linked to a company in Procore. Linked must be un-linked through the company tab in the Company level ERP Integrations tool before they can be archived.

    • If a vendor is marked as 'Inactive' in Yardi Voyager®, you can view it by clicking the 'Archived' link in the filters menu on the right of the vendor subtab.

Commitments

Yardi Voyager® support the sync of subcontract and purchase order. You must contact your integration implementation specialist or enterprise resource planning support before beginning to sync purchase order so that the appropriate configurations can be enabled.


Exporting a commitment to Yardi Voyager®

  • Prerequisites:

    • Configure the enterprise resource planning integration tool for Yardi Voyager®.

    • The commitment tool must be an active tab on the project.

    • When entering your commitment data, be aware of the following requirement:

      • Title. Yardi Voyager® limits commitment titles to a maximum of 30 characters. Titles exceeding this limit will be truncated in Yardi Voyager®.

  • Additional Information:

    • You can export commitments with sub jobs on the bill of quantities (BOQ) line items.

  • Limitations:

    • To sync a commitment, all bill of quantities (BOQ) line items must be tied to cost codes and categories from your ERP-synced lists of standard cost codes and cost types.

    • Commitment synced to Yardi Voyager® will NOT contain details regarding tax code.

    • Contract ID has a max character limit of 16.

    • Contract description has a max character limit of 30.

    • The Contract ID for purchase orders must be shorter than 8 characters.

Commitment variation

Yardi Voyager® support the sync of CVs for subcontract and purchase order.


Accept or reject a CV for export to
Yardi Voyager®

  • Prerequisites:

    • The company account must be integrated with Yardi Voyager®.

    • The variations and commitments tool must be an active tab on the project.


Export a CV to
Yardi Voyager®

  • Additional Information:

    • You can export CV's with sub jobs on the Bill of Quantities (BOQ) line item.

  • Limitations:

    • To add a bill of quantities (BOQ) line item to a CV, it must be tied to an existing cost code and category.

    • If a line item on a CV creates a new line item on the original contract, that new line item will not be reflected on the Yardi Voyager® contract. However, the CV's line item will still be sent to Yardi Voyager®.

    • Variation ID has a max character limit of 16.

    • Variation description has a max character limit of 30.

Subcontractor payment applications

Yardi Voyager® support the sync of subcontractor payment applications. Purchase order payment applications are not supported at this time.


Export subcontractor payment applications from Procore to
Yardi Voyager®

  • Additional Information:

    • You can export subcontractor payment applications with sub jobs on the Bill of Quantities (BOQ) line items.

  • Limitations:

    • Payment applications whose total amount equals zero pounds cannot be sent to Yardi Voyager®. These payment applications will not be synced when exported.

    • Materials presently stored and materials retention are not supported with the Yardi Voyager® integration. These values will be ignored when sending payment applications to Yardi Voyager®.

    • Yardi Voyager® cannot accept images alongside payment applications sent from Procore. Instead, Procore will send a link to the payment application within Procore, so that Yardi Voyager® users can view all related documentation. This will require that those Yardi Voyager® users have the correct permissions in Procore.

Direct Costs

Import direct costs and payment application payments across all projects from Yardi Voyager® to Procore

  • Add a 'direct costs' source column to your Procore project's budget view
    Provides authorised users with the ability to add a 'direct costs' column to your project's budget view.

  • Configure which direct cost appear in a given budget view column
    Provides authorised user with the ability to configure which direct cost appear in each column with a 'direct cost' source. For the integration with Yardi Voyager®, direct cost of the following types are available to configure:

    • Subcontractor payment applications: These direct costs come from Yardi Voyager® payables with an associated commitment.

    • Payment applications: These direct costs come from Yardi Voyager® Payables without an associated commitment.

    • Expenses: These direct costs come from Yardi Voyager® journal entries.

  • Track Yardi Voyager® direct costs in a Procore budget
    Once the 'direct costs' column has been added to a budget view, project users with access permissions to the budget can view the lump sum totals from the Yardi Voyager® job cost transactions as a direct cost value on a budget line item. The value in this column shows your project's 'direct costs' total for all items in the 'Pending', 'Revise and Resubmit' and 'Approved' status.
    Note: An accounting approver can sync the job cost transaction details from Yardi Voyager® on the Job cost tab of the Company level ERP integration tool.

  • View direct cost transaction detail on a budget line item
    Project users with the 'View direct cost details' granular permission enabled on their permission template can click the link in the direct cost column of a budget line item to open the direct cost's details. This granular permission is located in the 'Budget' section when configuring a permission template.

  • Import Yardi Voyager® direct costs in a Procore Budget
    You can import direct costs from Yardi Voyager® with Bill of Quantities (BOQ) line items across multiple projects.
    Note: If the direct cost is imported from a journal entry, separate direct cost transactions will be created in Procore. For example, if a journal entry has three line items for different sub jobs, Procore will split these line items into three direct cost transactions during sync.

  • Direct cost from Yardi Voyager® Payables are split as subcontractor payment applications or payment applications
    During the import of direct cost from Yardi Voyager® Payables, line items are categorised into different direct cost types based on their contract IDs as follows:

    • Subcontractor payment application: Line items with contract IDs are imported as subcontractor payment applications.
      Note: Procore does not import direct costs for multiple line items with unique contract IDs as separate subcontractor payment applications. Consequently, direct costs for multiple line items with different contract IDs are imported as a single subcontractor payment application to Procore.

    • Payment application: Line items without contract IDs are imported as payment applications.