Things to know
Background
Each of Procore's available ERP connectors perform the basic function of syncing data between the ERP system and Procore, usually in the same way as other connectors. However, each connector has a unique set of items it can sync and the way those items are synced will vary based on how that ERP system and its corresponding integration are built to function.
Yardi Voyager®, like all ERP integrations, has some key considerations, limitations and things to know about how each Procore object is synced. Those considerations, limitations and things to know are outlined in the table below according to tool or item being synced.
Things to know about the Yardi Voyager® Connector
Procore item or setting | Considerations, limitations and requirements |
|---|---|
Configuration settings & sync programme |
|
Cost codes/cost types | Add cost code to import to Procore
|
Projects | Important
|
Sub jobs |
|
Project level work breakdown structure (WBS) |
|
Budget |
|
Budget Changes | You can export budget changes with sub jobs on the Bill of Quantities (BOQ) line items. |
Companies | Import companies to Procore
|
Commitments | Yardi Voyager® support the sync of subcontract and purchase order. You must contact your integration implementation specialist or enterprise resource planning support before beginning to sync purchase order so that the appropriate configurations can be enabled.
|
Commitment variation | Yardi Voyager® support the sync of CVs for subcontract and purchase order.
|
Subcontractor payment applications | Yardi Voyager® support the sync of subcontractor payment applications. Purchase order payment applications are not supported at this time.
|
Direct Costs | Import direct costs and payment application payments across all projects from Yardi Voyager® to Procore
|