Which fields in the Daily Log tool can be configured as required, optional, or hidden?
Background
Certain fields in the Daily Log tool can be configured as required, optional, or hidden. For example, if you want to make comments required, or hide a section that is not relevant to you and your team, you can configure these preferences in the Company level Admin tool and then apply them to one or more projects.
See Create New Configurable Fieldsets.
Answer
The tables below detail which fields can be configured for sections in the project's Daily Log tool:
Accidents
Call
Daily Construction Report
Delay
Delivery
Dumpster
Equipment
Inspection
Manpower
Notes
Observed Weather Conditions
Plan Revision
Productivity
Quantity
Safety Violation
Visitors
Waste
Work
Note:
A GREEN checkmark
indicates the field can be configured to this setting.A RED 'x'
indicates the field cannot be configured to this setting.A field name in GRAY italics indicates the field cannot be configured from its default setting.
Accidents
Nombre del campo | Obligatorio | Opcional | Escondido |
|---|---|---|---|
Accesorios |
|
|
|
Comentarios |
|
|
|
Empresa involucrada |
|
|
|
Hora |
|
|
|
Minuto |
|
|
|
Parte involucrada |
|
|
|
Call Log
Field Name | Required | Optional | Hidden |
|---|---|---|---|
Attachments |
|
|
|
Comments |
|
|
|
Call From |
|
|
|
Call To |
|
|
|
End Hour |
|
|
|
End Minute |
|
|
|
Start Hour |
|
|
|
Start Minute |
|
|
|
Daily Construction Report
Nombre del campo | Obligatorio | Opcional | Escondido |
|---|---|---|---|
Accesorios |
|
|
|
Comentarios |
|
|
|
Compañía |
|
|
|
Horas de aprendiz de primer año 1 |
|
|
|
Horas totales de Capataz |
|
|
|
oficial Horas totales |
|
|
|
Horario para residentes locales (ciudad) 1 |
|
|
|
Horas de residente local (condado) 1 |
|
|
|
Horas de minorías 1 |
|
|
|
Otras horas totales |
|
|
|
Comercio |
|
|
|
Horas de Veteranos 1 |
|
|
|
Horas Mujeres 1 |
|
|
|
1 By default, the following workforce labor types are not included in the Daily Construction Report: Women, Veteran, Minority, First-Year Apprentice, Local (City), and Local (County). In order to have them available for use in a project, you will need to mark them as 'Required' or 'Optional', and apply the settings to one or more projects.
See How do I enable additional workforce labor types for the Daily Log?
Delay
Nombre del campo | Obligatorio | Opcional | Escondido |
|---|---|---|---|
Accesorios |
|
|
|
Comentarios |
|
|
|
Tipo de retardo |
|
|
|
Hora de finalización |
|
|
|
Ubicación |
|
|
|
Hora de comienzo |
|
|
|
Delivery
Field Name | Required | Optional | Hidden |
|---|---|---|---|
Attachments |
|
|
|
Comments |
|
|
|
Contents |
|
|
|
Delivery From |
|
|
|
Time Hour |
|
|
|
Time Minute |
|
|
|
Tracking Number |
|
|
|
Dumpster
Field Name | Required | Optional | Hidden |
|---|---|---|---|
Attachments |
|
|
|
Comments |
|
|
|
Company |
|
|
|
# Delivered |
|
|
|
# Removed |
|
|
|
Equipment
Field Name | Required | Optional | Hidden |
|---|---|---|---|
Attachments |
|
|
|
Comments |
|
|
|
Cost Code |
|
|
|
Equipment Name |
|
|
|
Hours Idle |
|
|
|
Hours Operating |
|
|
|
Inspected |
|
|
|
Inspection Hour |
|
|
|
Inspection Minute |
|
|
|
Location |
|
|
|
In Beta
Company Administrators can enable the Improved Equipment Time Tracking in Procore Explore. (US 2 | UK)
This beta allows you to define custom fields for equipment time entries and automatically sync them to the daily log.
Steps: To sync Equipment Timesheets with Daily Log entries, the configurable fieldset for Daily Log Equipment Entries must match the Equipment fieldset for Timesheets.
Inspection
Nombre del campo | Obligatorio | Opcional | Escondido |
|---|---|---|---|
Accesorios |
|
|
|
Comentarios |
|
|
|
Área |
|
|
|
Hora de finalización |
|
|
|
Fin del minuto |
|
|
|
Entidad inspectora |
|
|
|
Tipo de inspección |
|
|
|
Nombre del inspector |
|
|
|
Ubicación |
|
|
|
Hora de inicio |
|
|
|
Minuta de inicio |
|
|
|
Manpower
Nombre del campo | Obligatorio | Opcional | Escondido |
|---|---|---|---|
Accesorios |
|
|
|
Comentarios |
|
|
|
Compañía |
|
|
|
Código de costo |
|
|
|
Horas |
|
|
|
Ubicación |
|
|
|
Comercio |
|
|
|
Trabajadores |
|
|
|
Notes
Field Name | Required | Optional | Hidden |
|---|---|---|---|
Attachments |
|
|
|
Comments |
|
|
|
Issue? |
|
|
|
Location |
|
|
|
Observed Weather Conditions
Nombre del campo | Obligatorio | Opcional | Escondido |
|---|---|---|---|
Accesorios |
|
|
|
Promedio |
|
|
|
Comentarios |
|
|
|
Demorar |
|
|
|
Tierra/Mar |
|
|
|
Precipitación |
|
|
|
Cielo |
|
|
|
Temperatura |
|
|
|
Tiempo observado |
|
|
|
Viento |
|
|
|
Plan revision
Field Name | Required | Optional | Hidden |
|---|---|---|---|
Attachments |
|
|
|
Comments |
|
|
|
Category |
|
|
|
Plan Revision |
|
|
|
Revision |
|
|
|
Title |
|
|
|
Productivity
Field Name | Required | Optional | Hidden |
|---|---|---|---|
Attachments |
|
|
|
Comments |
|
|
|
Line Item |
|
|
|
Quantity Delivered |
|
|
|
Quantity Put in Place |
|
|
|
Quantity
Nombre del campo | Obligatorio | Opcional | Escondido |
|---|---|---|---|
Accesorios |
|
|
|
Comentarios |
|
|
|
Código de costo |
|
|
|
Ubicación |
|
|
|
Cantidad |
|
|
|
Unidades |
|
|
|
Safety Violations
Field Name | Required | Optional | Hidden |
|---|---|---|---|
Attachments |
|
|
|
Comments |
|
|
|
Compliance Due |
|
|
|
Hour |
|
|
|
Issued To |
|
|
|
Minute |
|
|
|
Safety Notice |
|
|
|
Subject |
|
|
|
Visitors
Nombre del campo | Obligatorio | Opcional | Escondido |
|---|---|---|---|
Comentarios |
|
|
|
Fin |
|
|
|
Empezar |
|
|
|
Visitantes |
|
|
|
Waste
Field Name | Required | Optional | Hidden |
|---|---|---|---|
Attachments |
|
|
|
Comments |
|
|
|
Approximate Quantity |
|
|
|
Disposal Location |
|
|
|
Disposed By |
|
|
|
Hour |
|
|
|
Material |
|
|
|
Method of Disposal |
|
|
|
Minute |
|
|
|
Work
Field Name | Required | Optional | Hidden |
|---|---|---|---|
Attachments |
|
|
|
Comments |
|
|
|
Hours |
|
|
|
Rate |
|
|
|
Reimbursable |
|
|
|
Resource |
|
|
|
Showed? |
|
|
|
Workers |
|
|
|