Things to Know
Background
Each of Procore's available ERP connectors performs the basic function of syncing data between the ERP system and Procore, usually in the same way as other connectors. However, each connector has a unique set of items it can sync, and the way those items are synced will vary based on how that ERP system and its corresponding integration are built to function.
Procore Edge for Acumatica®, like all ERP integrations, has some key considerations, limitations, and things to know about how each Procore object is synced. Those considerations, limitations, and things to know are outlined in the table below according to the tool or item being synced.
Availability of ERP connectors is dependent on several factors, including the country or region in which your business operates. To learn whether or not an integration is available in your area, contact your Procore point of contact.
Things to know about the Procore Edge Connector for Acumatica®
Procore Item or Setting | Considerations, Limitations, and Requirements |
|---|---|
Configuration Settings |
|
Sync Schedule | Data Exchange Frequency
|
Company Level Work Breakdown Structure (WBS) | Considerations
|
Project Level Work Breakdown Structure (WBS) | Limitations
|
Companies | Import Companies to Procore
|
Projects | Limitations
|
Sub Jobs | Limitations
|
Budget | Prerequisites for Export from Procore
|
Budget Changes | Considerations
|
Commitments | Considerations
|
Commitment Change Orders | Considerations
|
Subcontractor Invoices | Prerequisites
|
Prime Contracts | Prerequisites & Limitations Prime contracts in Procore automatically sync to Procore Edge for Acumatica® as a summarized single line item within the Revenue Budget tab. Your prime contract is automatically synced when the following conditions are met:
Any changes made to the overall value of the contract after the initial contract value is synced must be manually updated in the ERP system.
In order to sync a Prime Contract with the Acumatica ERP Connector, the 'Revenue Budget Level' setting on the ERP Job’s 'Summary' tab must be set to 'Task' only. |
Prime Contract Change Orders | Requirements
|
Job Costs | Prerequisites
|