Send Requests for Quote (RFQs) to Multiple Assignees

Background

Beta

This feature is currently in open beta and is available to Procore customers by opting through Procore Explore.

In standard construction workflows, assigning an individual point of contact to a Request for Quote (RFQ) can delay responses if that person is out of the office, leaves the company, or shares quoting responsibilities with a team. To prevent delays, you can select multiple assignees when sending an RFQ. This ensures all relevant team members and subcontractor representatives receive notifications and can submit a quote on behalf of their organization.

Things to Consider

  • Required Permissions:

    • 'Standard' or 'Admin' level permissions on the project's Change Events tool or Commitments tool.

  • Additional Information:

    • When you send an RFQ to multiple assignees, all selected assignees receive an email notification at the same time.

    • You can use the multi-assignee feature directly from the RFQ commitment view or when creating RFQs from a change event.

  • Ball In Court Responsibility:

    • After any assignee submits a quote, Ball In Court responsibility automatically transfers back to the General Contractor (GC).

    • When the GC responds or requests a revision, Ball In Court responsibility defaults to the individual who submitted the most recent response. For example, if a user submitted the last quote, the follow-up routes directly to that user.

  • You can use the multi-assignee feature directly from the RFQ commitment view.

Prerequisites

Create a draft RFQ or open an existing draft RFQ in the project's Commitments tool or Change Events tool. To learn more, Create RFQs from a Change Event or Create a Request for Quote (RFQ).

Steps

Step 1: Create and Send an RFQ to Multiple Assignees

  1. Navigate to the project's Commitments tool or Change Events tool.

  2. Create and draft a new RFQ or open an existing draft RFQ.

  3. Click the Assignees field and select the team members and subcontractor representatives you want to include.

  4. Click Send or Create and Send RFQs to send an email notification to all selected assignees.

Step 2: Track Assignees from the List View

  1. Navigate to the RFQ list view in the Commitments or Change Events tool.

  2. Locate the multi-assignee indicator in the RFQ table.

  3. Hover your cursor over an assignee's name or the assignee count to view their email address and phone number.

Step 3: Manage Subcontractor Responses and Revisions

  1. Have any designated assignee open the RFQ from their email notification or in Procore to enter and submit a quote.

    Note

    After an assignee submits a quote, Ball In Court responsibility automatically transfers to the GC.

  2. To request changes, click Revise & Resubmit to route the RFQ back to the assignee who submitted the most recent response.

  3. Optional: If the primary responder is unavailable, any other assigned user can submit the requested revision. Submitting a revision updates the activity log and transfers Ball In Court responsibility back to the GC.

See Also