Este sitio web aún no se ha lanzado completamente en tu configuración regional preferida
La única página disponible en tu configuración regional preferida del sitio de soporte V2 es la página de la biblioteca de videos. El lanzamiento completo del sitio web llegará pronto.
¿Buscas otro contenido? Vuelve al sitio de soporte V1.
If your company is using the ERP Integrations tool: Show/Hide
Not all ERP integrations support the sync of change orders. For those that do, additional requirements, limitations, and considerations vary depending on the ERP system your company's account is integrated with. See Things to Know About your ERP Integration for details.
How do you collect signatures with DocuSign? After the data entry for the subcontract is complete, change its status to 'Approved' and click the Complete with DocuSign button. This launches the DocuSign® application. If you have not previously signed in, you will be prompted to Sign In to DocuSign®. After you are signed in, you can proceed with Prepare a DocuSign® Envelope for Signature.
Change Order # Accept the default contract number, enter a new number for this contract, or create a custom numbering scheme for this contract and future contracts.
Notes
If you plan to create multiple change orders, Procore automatically assigns new numbers in sequential order. For example; 001, 002, 003, and so on.
To use a custom numbering scheme, enter any set of alphanumeric characters and Procore automatically assigns new numbers in sequential order using your custom scheme. For example, enter FCO-1, FCO-01, or FCO-001.
Date Created Shows the date and time the funding change order was created. You cannot change this date.
Revision Displays the funding change order's revision number. When a funding change order is first created, its revision number is zero (0). A funding change order could have multiple revisions because of feedback from a reviewer/approver.
Created By Displays the name of the user that created the funding change order. You cannot change this name.
Private Mark this checkbox if you want to make the funding change order 'Private' and visible only to users with 'Admin' on the Funding tool.
Due Date Select a due date for when the funding change order must be approved by.
Invoiced Date Select the date when the funding change order was invoiced.
Designated Reviewer Select the Procore project user at your organization who will be responsible for approving or rejecting this funding change order later.
Important
The 'Designated Reviewer' can submit an approve or reject response when a change order is in these statuses:
Pending - In Review
Pending - Revised
To send an email notification to the 'Designated Reviewer' to notify that person that a change order is awaiting their response, you have these options:
The pending funding change order will also be listed in the 'My Open Items' area in the Project Home page.
After the 'Designated Reviewer' submits an approve or reject response, the 'Reviewer' field (directly below the 'Designated Reviewer' field) shows the date/time stamp of that person's response. The 'Reviewer' field is only visible to the 'Designated Reviewer.'
Paid Date Select the date that payment was received for the funding change order.
Description Enter a more detailed description of the funding change order.
Schedule Impact If this funding change order is expected to impact the construction project's schedule, enter the estimated number of additional days this would add to the schedule.
Revised Substantial Completion Date Enter an updated substantial completion date for the project.
Note
If the substantial completion date is enabled on the Funding tool, Procore updates the funding change order's 'Revised Substantial Completion Date' field after the funding change order is placed into the Approved status. See Configure Settings: Funding.
Executed Mark this checkbox after the funding change order is fully executed.
Potential Change Orders If the Funding tool is configured for two (2)-tier change orders, select any potential change orders related to this funding change order from this drop-down list. See Configure the Number of Change Order Tiers for the Funding Tool.
Choose one (1) of these options:
To create the funding change order, click Create. OR
To create the funding change order and send email notifications, click Create & Email.