Choose an "Official Response" for an RFI

Background

Several people may need to respond to an RFI before a correct answer can be provided. For example, an Architect may need to get feedback and clarification from the Owner or a Consultant/Specialist before they can provide an authorized answer. As a result, each RFI can have a long communication thread that may be difficult for some team members or collaborators to interpret correctly. In such cases, users with the appropriate permissions (such as Project Manager/Engineers) can highlight the correct answer by marking one or more replies in the activity thread as the "official response" for an RFI.

Temas a considerar

  • Permisos de usuario necesarios

  • Información adicional:

    • Puede seleccionar más de una respuesta como "Respuesta oficial".

    • Si aún no es obvio qué respuesta debe marcarse como "respuesta oficial", el director de proyectos/ingeniero debe responder a la RFI y pedir a las personas asignadas que resuman los hallazgos e indiquen claramente la respuesta correcta en una nueva respuesta. Para evitar interpretaciones erróneas y problemas relacionados con la responsabilidad, un director de proyectos/ingeniero no debe intentar interpretar todas las respuestas, resumir la respuesta y seleccionar su propia respuesta como la "respuesta oficial" para una RFI.

Steps

  1. Navigate to the project's RFIs tool.

  2. Navigate to the Items tab.

  3. Click View next to the RFI you want to select an official response for.

  4. Scroll to the Responses card.

  5. Mark the Mark Official checkbox next to one or more responses.

 Tip

If the RFI is linked to a published markup in a drawing, the official responses will display at the top of the markup details. See Link Items on a Drawing.

Siguiente paso

See Also

Loading related articles...