Which Procore tools can I extract project data from using the Data Extracts 2.0 tool?

Answer

Currently, the Data Extracts 2.0 tool can extract a copy of data from the following tools so that you can have a record of these items outside of Procore:
Note: An asterisk (*) denotes that you cannot choose whether to include attachments associated with the tool's items in the extract.

Procore Tools

Details

Action Plans

Extracts all action plans that exist in the project's Action Plans tool.

Bids

Extracts all bids that exist in the project's Bidding tool.

Change Events

Extracts all change events that exist in the project's Change Events tool.

Change Orders*

Extracts all change orders that exist in the Change Orders tool. Change orders are created in the project's Commitments and Prime Contract tools.

Correspondence

Extracts all correspondences that exist in the project's Correspondence tool.

Daily Log

Extracts a daily summary for each day of the project. See Daily Log.

Directory*

Extracts all contact data that exists in the project's Directory tool.

Documents*

Extracts all documents that exist in the project's Documents tool.

Drawings

Extracts all drawings that exist in the project's Drawings tool.

Emails

Extracts all email messages that exist in the project's Emails tool.

Forms

Extracts all forms that exist in the project's Forms tool.

Incidents

Extracts all incidents that exist in the project's Incidents tool.

Inspections

Extracts all inspections that exist in the project's Inspections tool.

Meetings

Extracts all meetings that exist in the project's Meetings tool.

Models*

Extracts all models that exist in the project's Models tool.

Observations

Extracts all observations that exist in the Observations tool.

Photos*

Extracts all photos that exist in the project's Photos tool.

Prime Contract Invoices

Extracts all owner invoices that exist in the project's Invoicing tool.

Prime Contracts

Extracts all prime contracts that exist in the project's Prime Contracts tool.

Punch List

Extracts all punch items that exist in the project's Punch List tool.

Purchase Orders

Extracts all purchase orders that exist in the project's Commitments tool.

RFIs

Extracts all RFIs that exist in the project's RFIs tool.

Specifications*

Extracts all specifications that exist in the project's Specifications tool.

Subcontractor Invoices

Extracts all subcontractor invoices that exist in the project's Invoicing tool.

Subcontracts

Extracts all subcontracts that exist in the project's Commitments tool.

Submittals

Extracts all submittals that exist in the project's Submittals tool.