Create a Purchase Order
Background
In Procore, a Purchase Order (PO) is a formal financial commitment documenting the specific types, quantities, and agreed-upon prices for products or services. These orders are an essential part of the procurement process. A buyer (for example, a General Contractor) creates and issues a PO to a seller (for example, a Subcontractor) to cover the cost of a contract. Once the seller accepts the PO, it represents an agreement between both parties.
Things to Consider
Required User Permissions:
To create a Purchase Order and view or enter data on the Schedule of Values (SOV) tab, you must meet one of the following requirements:
Admin level permissions on the project's Commitments tool.
ORStandard level permissions on the project's Commitments tool, AND the Allow Users to See SOV Items setting must be enabled with your name selected in the Select a Person drop-down list.
For companies using the
ERP Integrations tool: Prerequisites, requirements, limitations, and specific considerations may be applicable, depending on the particular ERP system integrated with your Procore account.
Prerequisites
Steps
Navigate to the project's Commitments tool.
On the Contracts tab, click the Create button and choose Purchase Order from the drop-down list.
Note
The Create button is available when you are viewing the Contracts and Recycle Bin tabs. New purchase orders are always added to the Contracts tab.
The Export button is only available on the Contracts tab. To learn more, see Export a Commitments List.

Enter the following information and save the contract.
If you do NOT number your contracts using sequential numbering, you can manually enter a unique number for each purchase order. To do this, type over the existing entry in the Number box. Duplicate contract numbers are NOT permitted.
Notes
For companies using the ERP Integrations tool, your integrated ERP system may impose a maximum character limit. See What is the maximum character length for a commitment's 'Number (#)'? Important! When a commitment is exported to Integration by Procore, it must have a unique number.
You can customize the numbering scheme for your project's commitments. To learn more, see Can I customize the numbering system for financial objects in Procore?