Create a Transfer
Background
If you need to move materials to a new storage location, you can create a materials transfer. If the status of materials changes during the transfer, 'Quantity Available' inventory counts are updated accordingly.
Things to Consider
You can have multiple line items with different locations in a single transfer.
After you submit a transfer and the status is 'Final', you can only edit the following fields:
Attach files
Custom Fields
Notes
Post Transfer Condition
'Quantity Available' counts are updated when the transfer is submitted and the status is 'Final'.
Post-Transfer Item Condition
Quantities of 'Acceptable' materials are included in the 'Quantity Available' in your inventory.
Quantities of 'Damaged' and 'Unacceptable' Materials are excluded from the 'Quantity Available' in your inventory.
Steps
Navigate to the project's Materials tool.
Click the Inventory tab.
Mark the checkbox next to the materials you want to transfer.
Click Add to New Document and select Transfer.
Enter the general transfer information.
Enter the transfer for each line item.
Save or submit the transfer.
Click Save as Draft to save the adjustment as a draft.
Click Submit to submit the adjustment for approval.