Edit Direct Costs on the Uploads Tab

Background

Beta

This content is for participants in the Project Financials: Company Direct Costs beta program.


Before you submit documents for review, you can edit the direct costs details in the Uploads tab. This ensures your data is accurate before it moves to the Direct Cost tab for final review and approval process.

Things to Consider

  • Required User Permissions:

    • 'Admin' or ‘Standard’ level permissions on the Company level Direct Costs tool.

  • Additional Information:

    • Ensure the direct cost to edit is visible on the list in Uploads tab.

Steps

  1. Navigate to the Company level Direct Cost tool.

  2. Locate the Direct Cost to Edit.

  3. Click the check box next to the direct cost entry and Click Edit button.
    Note: Use the Search bar to find the direct cost you want to edit.
    Alternatively, click the direct cost’s name to open the Edit Direct Cost page.

  4. Edit the following information in the General Information section:

    Field Name

    Description

    Vendor Direct Cost Number

    Specify the Vendor Direct Cost Number.

    Vendor

    Select the Vendor from the drop-down list.

    Direct Cost Type

    Select the Direct Cost Type from the drop-down list.

    Received Date

    The date the invoice was received or uploaded.

    Invoice Date

    The date from the Invoice PDF will be displayed in the Date field when viewing the direct costs details within the Budget Tool.

    Accounting Date

    The accounting date the invoice was received or uploaded.

    Description

    Enter the description.

  5. Complete the entries in Line Items section:

    Field Name

    Description

    Billed Amount

    Specify the total amount billed for the invoice.
    Note: The total value of the Line Items must equal the billed amount for the request to be approved

    Project

    Selecting the project from the drop-down list determines the available budget codes for the line items, ensuring costs are accurately assigned to the correct project for review.

    Budget Code

    Select the appropriate budget code from the drop-down list or Search by entering the unique budget code identifier and choose the appropriate budget code from the drop-down list. 

    Units

    Enter the number of units to bill. This field defaults to 1.Specify the number of units being billed.

    UOM

    Select the Unit of Measure (UOM) for the item. This field defaults to each. Select the Unit of Measure that applies to the item.

    Unit Cost

    Enter the cost per individual unit.

    Amount

    The amount is calculated based on the units and unit cost.

    Description

    Enter details related to this line item entry.

    Line Items Total

    The total amount calculated for this item.

    Amount to Allocate

    Enter the portion of the total amount you want to distribute.

  6. The Attachments section displays the uploaded file; click Attach File to upload any relevant files required for review or approval. 

  7. Edit the following information in the Payments section:

    Field Name

    Description

    Payment Terms

    Enter the agreed conditions under which the payment should be made.

    Payment Due Date

    The final date by which the payment must be completed.

    Discount Date

    The date by which the payment must be made to take advantage of any vendor discounts. The date by which the payment must be made to avail any discount..

    Payment Status

    Select the current status of the payment. Options include Unpaid, Partially Paid, or Paid. Indicate the current status of the payment (Unpaid, Partially Paid, Paid)

    Payment Date

    Enter the date of the most recent payment. The date on which the payment was actually made.

  8. Click Save & Close, saves your changes and closes the window.

  9. Click sends the direct cost record to the reviewer for approval.

See Also