Background
You can add adjustments to your estimates by creating your own calculations for different pre and post-tax markups. Currently these adjustments are shown in the proposal, without an option to hide them.
Example
You want to tax the cost of materials only (not including profit) at 5%, you would create a pre-tax mark up with the following settings:
Type: Basic Calculation
Percent: 5
Application Criteria: Cost Type Includes Materials
You want to add 10% margin for the total final cost of the estimate, you would create a post-tax mark up with the following settings:
Type: Iterative Calculation Margin
Percent: 10
Things to Consider
Required User Permissions for the Bid Board tool.
Required User Permissions for the Estimating tool.
Required User Permissions for the Portfolio Planning tool.
Currently adjustments are shown in the proposal, without an option to hide them.
Only pre-tax adjustments can have taxes applied to the markup.