Add Quantities to a Timesheet (iOS)
Background
Production quantities are a measurable amount of work on a construction project. For example, cubic yards of concrete, number of light fixtures, or linear feet of piping. In Procore, there are two types of production quantities:
Budgeted production quantities refers to the measurable amount a team plans to install on a project.
Installed production quantities refers to the actual amount installed on a project by a point in time.
After installed production quantities have been entered in a timesheet, they can be tracked against the imported budgeted production quantities using the Production Quantity Report.
Things to Consider
For customers using Procore Project Financials, you have the option to allow the quantities entered on a timesheet to interact with the 'Procore Labor Productivity Cost' budget view. To learn more, see Set Up the Procore Labor Productivity Cost Budget View.
The data entered in the Budgeted Quantity import will pull in the Unit of Measure and Percent Complete based on the cost code.
If Sub Jobs are enabled on your project, the 'Sub Job' associated with your 'Units Installed' entry will appear in the Add Quantities window. If Sub Jobs is disabled, the 'Sub Job' field will display the word 'None.'
Prerequisites
Steps
After you fill out your timesheet, perform the following actions before you submit:
Tap Submit.
Tap Submit and Add Quantities.
Tap the Quantities field and enter the number of items installed for the day.
Click Submit.