Compare Lookahead to Master Schedule
Background
When you work in a Lookahead, you are managing a granular field plan that lives "on top" of the master schedule. To ensure the field team stays aligned with the project's overall goals, Procore uses Shadow Bars. These allow you to see the original master schedule dates behind your active field tasks, making it immediately obvious if your current plan is deviating from the master timeline.
Things to Consider
Color Logic:
Colorful Bars: Represent your active field plan (the lookahead tasks).
Light Gray Shadow Bars: Represent the dates currently set in the Master Schedule.
Dynamic Updates: If the Master Schedule is re-imported (Option 1) or edited, the gray shadow bars will shift automatically, while your colorful field bars remain in place for comparison.
Updating an existing schedule: Re-importing completely overwrites and replaces the previously uploaded schedule—it does not append or add to existing data. You can upload updated files directly.
Uploading a schedule with different tasks: If your new schedule contains different/restructured tasks, you must Reset the Project Schedule first to avoid task-matching errors.