Fetch and Verify Lookahead Activities
Background
Fetching and verifying lookahead activities allows project teams to import upcoming tasks from the master schedule into a localized lookahead view to review, update, and confirm real-world task progress. This process ensures field operations stay aligned with overall project timelines while maintaining high schedule health and identifying data discrepancies before sharing schedule reports.
Things to Consider
Required User Permissions:
'Standard' level permissions or higher for the Scheduling tool.
Additional Information:
Lookahead tracking features are fully supported for master schedules natively uploaded via standard formats (.mpp, .xer) as well as the new Asta Powerproject (.pp) and MS Project XML (.xml) beta formats. To enable this beta, go to Manage Features With Procore.
Updating an existing schedule: Re-importing completely overwrites and replaces the previously uploaded schedule—it does not append or add to existing data. You can upload updated files directly.
Uploading a schedule with different tasks: If your new schedule contains different/restructured tasks, you must Reset the Project Schedule first to avoid task-matching errors.