Add an End Step (Successful)

An End Step (Successful) concludes the workflow and signifies a successful outcome. For example, a project item is 'Approved' or 'Approved as Noted.'

  1. In the Workflow Builder, click Icon Blue Plus Pfcp in an existing step and choose End Step (Successful).

  2. Under General Information, do the following:

    • Step Name. Enter a name for the workflow step.

    • Item Status. Select the status that shows successful completion. Status options vary for each item in the Procore tool.

    • Optional: Notification Recipients . Select which groups or roles Procore will automatically notify when the step is complete. The selections include:

  3. Click one (1) of these options:

    • Cancel. Discards any changes made.

    • Save as Draft. Saves a 'Draft' version with a minor version number (e.g., 0.1, 0.2, 0.3, and so on). Select this option if the workflow template is still under development.

    • Save and Publish. Creates a major version number for the workflow (e.g., 1.0, 2.0, 3.0, and so on). Choose this option when the workflow is ready for implementation and project assignment.

Save the Template

 Wichtig

Procore empfiehlt dringend, Ihren Fortschritt mit der Option Als Entwurf speichern zu speichern, während Sie Ihre Workflow-Vorlage erstellen. Dies ist eine bewährte Standardmethode, um Datenverluste aufgrund von versehentlichem Schließen, Browserproblemen oder anderen unvorhergesehenen Unterbrechungen zu minimieren.

  • Cancel. Discards any changes made.