Can I enable the change event tool on my existing project?

Answer

Yes, the change event tool can be enabled on existing projects. However, the method for enablement depends on whether variations already exist in the project.
Note: Once the change event tool is enabled, it can only be disabled via a request through your Procore point of contact.

Step 1: Check to see if any variations exist on the project

Before enabling the change events tool, determine if any variations have been created on the project. To view a list of variations on a project, follow these steps: View variations.

  • If variations have NOT been created on the project, you can skip steps 2 and 3 below and proceed with Step 4: Enable the change event tool.

  • If variations have been created on the project, you must complete Step 2: Request to run the variation migration process below.

Step 2: Request to run the variation migration process

If you discover that your users have already created variations on the project, your or a user with 'Admin' level permissions on the project's Admin tool must send an email to your company's Procore point of contact requesting to run Procore's variation migration process on your project.

The purpose of the migration process is:

  • To create a new change event for every main contract potential variation that exists.

  • To create new line item in each new change event for each line item on every main contract PV.

 Important
  • The variation migration process is best suited for clients who have configured the two (2)-tier variation setting on the main contract tool. See What are the different variation tiers in Project Financials?

  • It is less common for clients to configure the three (3)-tier variation tier setting on the main contract tool. However, most Procore clients who choose to configure three (3) tier (or more tiers) typically decide to leave the project's change event tool disabled on their projects.

Step 3: Variation migration & tool enablement

These step are performed for you by Procore. Your Procore point of contact will notify you when the migration process is complete and the tool has been enabled.

Step 4: Configure permissions and add to project template

  1. Update your default permission templates. See What are the default project permission templates in Procore? and Edit a project permission template.

    • To send a request for quote to your collaborators, you must provide those collaborator(s) with 'Standard' level permissions on the project's commitments tool.

    • To provide one of your employees with the ability to create a change event (for example, a foreman or site manager), those employees will need to be granted 'Standard' level permission on the project's change event tool.

    • Procore also recommends that you consider providing any appropriate employees with 'admin' level permissions on the project's change events tools.

    • To allow your project collaborators to submit variations, see Allow collaborators to submit site-initiated variations (Beta).

  2. Enable the tool on Procore's standard project template so the change event tool is turned ON in your company's new projects by default. See Edit a project template and Add and remove project tools.

 Tip

Thinking about disabling the change event tool? Be sure to review this FAQ first: Can I disable the change event tool?