How does the 'Actuals by date' filter work on a budget view?

Background

When you apply the 'Actuals by date' filter to a (see Apply the view, snapshot, group and filter options on a budget view), the filter updates the budget view to show only the cost, timesheet and production items that fall within the specific date range you define. When applying this filter to your budget view, keep in mind that the term By Date refers to dates that fall within the date range you specify and the term Actuals refers to:

  • Actual cost: The actual cost of the goods or services with the budget line item.

  • Actual unit-based quantity: The actual amount of materials associated with the budget line item.

The 'Actual costs by date' filter looks through the columns on your budget line items to determine which columns source data from specific project tools. It then limits the line items on the display to the actual costs and actual quantities falling within your specified date range.

Important things to note about this filter include:

  • It is important to keep in mind that the column data detailed below may also be used to configure calculated columns on the budget views in your environment.

  • Some cost, timesheet and production items in the Procore tool affected by this feature may not have a date associated with them. To include only the line items that have dates, mark the Only actuals with dates tickbox.

Answer

The 'Actuals By Date' filter considers budget line items that source data for columns from these Procore project tools:

  • All of the columns listed in the table below.

  • Any calculated column that use the columns below as part of the calculation.

Column name

Column format

Column type

Column description

Project Tool

Notes

Direct cost 1

currency

Source

Shows direct cost in the Pending, Revise and Resubmit and Approved status.

Direct Costs

The 'Date' field on a direct cost determines if an item will be filtered.

Subcontractor payment applications 2

currency

Source

Calculates the value in the 'job to date cost column of a budget view.

Payment applications

The 'billing date' for a subcontractor payment application determines if an item will be filtered.

Installed production quantity 3

Number

Source

Shows the quantity of installed production quantity for a budget code.

Budget

The 'Date Installed' value entered on the import template determines if production quantity will be filtered.

Timesheet hours 4

Number

Source

Shows all timecard entry hours.

Timesheets

The 'Date' field on a timesheet entry determines if its hours will be filtered.

1 For Procore customers using the ERP integration tools to sync job cost transactions into the project's direct cost tool, the 'Actuals By Date' filter lets you see all of the direct cost within the date range you selected.

2 For Procore customers using the project's Payment Applications tool, keep in mind that subcontractor payment application amounts are added to Procore's Budget tool cumulatively.

3 Production quantities must be entered on a timesheet directly or added using the Import installed production quantities feature on the Budget. Production quantities entered on a Site Diary entry are not linked to the Budget.

4 Timesheet hours generated from a Site Diary timecard entry are linked to the budget.

See Also

Loading related articles...