Glossary of key terms

  • Programme activity: The activity within the Project Programme that drives the deadlines for submittal review and approval.

  • Start date and finish date: The beginning and end dates of the programme activity as defined in the Procore Scheduling tool.

  • Required on-site date: The date by which materials associated with the submittal should be available at the job site.

  • Lead time: The duration required for material to become available on-site after the submittal’s final approval.

  • Final due date: The latest date a submittal can be approved while still ensuring materials arrive on-site on time.

  • Buffer time: Additional time built into the review process to account for potential delay or revisions.

  • Submit by date: The latest date by which the first step of the workflow (typically the submitter) should be completed.

  • Open by date: The latest date by which a submittal should be set to 'Open' status and the submitter notified.

  • BIC due date / workflow step due date: The deadline for the current 'Ball-in-Court' person to respond to their specific workflow step.