Change management without change events

After you build your commitment contracts, you can then create variations to account for additional cost. While most owners prefer to start out using the 2-tier variation tiers, the choice to configure it to use a 1-tier, 2-tier or 3-tier setting exists. More variation tiers make for a more complex workflow but provide an increased amount of control.

Funding tool enabled

  • What are the different variation tier settings in Project Financials?

  • Create a potential variation to outline any potential change in cost that would affect the funding. You can only enter a pound amount at the potential variation level. When you fill in a bill of quantities for a potential variation, you'll have the option to select a budget code. Ideally, it will be a budget code already in the Budget, so you can see the Budget increase on the Budget tab.

  • After creating a potential variation, you can create a commitment variation that acts as a request for pricing from the contractor who will be responsible for the scope of work outlined in the PV. You can compare the commitment variation to the corresponding potential variation and view your variance between the two.

  • After you've created funding potential variations, you can roll them into a variation request. Variation requests are typically the documents that are submitted for approval and can be used for submitting either individual potential variations or for grouping potential variations in order to streamline the review and approval process.

  • Once you have marked the commitment variations as approved, the pound change will be reflected in the "committed costs" column on the Budget tool. Commitments and potential commitment variations with a status of "Pending" will show up in the "pending cost changes" column on the Budget tool.

Funding tool disabled

  • You can only enter a pound amount at the potential variation level. When you fill in a bill of quantities for a potential variation, you'll have the option to select a cost code.

    • Create a variation request for a commitment.

    • Variations with a status set to "Pending" will appear in the "Pending budget changes" column on the Budget tool. Approved variations can be added to main contract payment applications. Once you have marked the variation as approved, the total pound amount change will be reflected in the "Approved COs" column on the Budget tool.

  • After creating a potential variation, you can create a commitment variation that acts as a request for pricing from the contractor who will be responsible for the scope of work outlined in the potential variation. You can compare the commitment variation to the corresponding potential variation and view your variance between the two.

  • Once you have marked the commitment variation as approved, the pound change will be reflected in the "committed costs" column on the Budget tool. Commitments and potential CVs with a status of "Pending" will show up in the "pending cost changes" column on the Budget tool.

For more information about the Variations tool, see Variations.