Delete a CV synced with enterprise resource planning

Enterprise resource planning documentation

Each Procore-built enterprise resource planning integration offers its own unique feature set. Your integration might not support the action described on this page.

To learn about your integration and its supported features, see Which ERP integrations are supported by Procore?

Background

After syncing a CV with your ERP system, users will typically follow the variation process when a CV needs to be modified. However, you might sometimes need to delete a synced CV on a project. Since Procore does not allow deletion of synced commitments, you must first unlink the records in the two systems before you can delete the CV.

Things to Consider

  • Required User Permissions:

    • 'admin' level permission on the project's commitment tool.

  • Limitations:

    • You cannot delete an 'Approved' variation.

    • After a synced CV is unlinked and deleted, the data is permanently removed from the system and cannot be restored.

  • Prerequisites:

Steps

  1. Navigate to the project's commitment tool.
    Note: Before proceeding, make sure the CV is unlinked. See Unlink CVs synced with enterprise resource planning.

  2. Locate the synced CV in the list.

  3. Click View or Edit.

  4. Update status to draft.

  5. Click Save.

  6. Return to the project's commitments main tool page.

  7. Locate the CV that you want to delete. Click Delete Icon Delete X.

See Also