If your company is using the ERP Integrations tool: Show/Hide
Not all ERP integrations support the sync of variations. For those that do, additional requirements, limitations and considerations vary depending on the ERP system your company's account is integrated with. See Things to know about your ERP integration for details.
How do you collect signatures with DocuSign? After the data entry for the subcontract is complete, change its status to 'Approved' and click the Complete with DocuSign button. This launches the DocuSign® application. If you have not previously signed in, you will be prompted to Sign in to DocuSign®. After you are signed in, you can proceed with Prepare a DocuSign® envelope for signature.
Variation # Accept the default contract number, enter a new number for this contract or create a custom numbering scheme for this contract and future contracts.
Notes
If you plan to create multiple variations, Procore automatically assigns new numbers in sequential order. For example; 001, 002, 003 and so on.
To use a custom numbering scheme, enter any set of alphanumeric characters and Procore automatically assigns new numbers in sequential order using your custom scheme. For example, enter funding variation-1, funding variation-01 or funding variation-001.
Date created Shows the date and time the funding variation was created. You cannot change this date.
Revision Displays the funding variation's revision number. When a funding variation is first created, its revision number is zero (0). A funding variation could have multiple revisions because of feedback from a reviewer/approver.
Created by Displays the name of the user that created the funding variation. You cannot change this name.
Private Mark this tickbox if you want to make the funding variation 'Private' and visible only to users with 'admin' on the funding tool.
Due date Select a due date for when the funding variation must be approved by.
Payment application date Select the date when the funding variation was payment application.
Designated reviewer Select the Procore project user at your organisation who will be responsible for approving or rejecting this funding variation later.
Important
The 'designated reviewer' can submit an approve or reject response when a variation is in these status:
Pending - in review
Pending - revised
To send an email notification to the 'designated reviewer' to notify that person that a variation is awaiting their response, you have these options:
The pending funding variation will also be listed in the 'My open items' area in the Project Home page.
After the 'designated reviewer' submits an approve or reject response, the 'Reviewer' field (directly below the 'designated reviewer' field) shows the date/time stamp of that person's response. The 'Reviewer' field is only visible to the 'designated reviewer.'
Paid date Select the date that payment was received for the funding variation.
Description Enter a more detailed description of the funding variation.
Programme impact If this funding variation is expected to impact the construction project's programme, enter the estimated number of additional days this would add to the programme.
Revised substantial completion date Enter an updated practical completion date for the project.
Note
If the substantial completion date is enabled on the funding tool, Procore update the funding variation's 'Revised substantial completion date' field after the funding variation is placed into the Approved status. See Configure setting: funding.
Executed Mark this tickbox after the funding variation is fully executed.
Potential variations If the funding tool is configured for two (2)-tier variations, select any potential variations related to this funding variation from this drop-down list. See Configure the number of variation tiers for the Funding tool.
Choose one (1) of these options:
To create the funding variation, click Create. OR
To create the funding variation and send email notifications, click Create & email.