Bulk edit subcontractor payment application status with the Payment Applications tool

Using owner or specialty contractor terminology?

Procore can be configured to use terminology specific to main contractors, owners or specialty contractors. Learn how to apply the dictionary options.

  • To learn the differences: Show/Hide

    • This table shows the differences in tool names (bold) and terms across the point-of-view dictionaries for Project Financials.

      Main Contractors
      English (United States) - Default

      Owners
      English (Owner Terminology V2)

      Speciality Contractors
      English (Speciality Contractor Terminology)

      Payment applications

      Payment applications

      Progress Billings

      Owner

      Funding

      Owner

      Owner/Client

      Owner/Client

      MC/Client

      Main Contract Variation

      Funding Variation

      Client Contract Variation

      Main Contracts

      Funding

      Client Contracts

      Revenue

      Funding

      Revenue

      Subcontract

      Contract

      Subcontract

      Subcontractor

      Contractor

      Subcontractor

      Subcontractor Bill of Quantities (SBOQ)

      Contractor Bill of Quantities (CBOQ)

      Subcontractor Bill of Quantities (SBOQ)

      About these dictionaries
      • Default setting: The 'main contractor' dictionary is enabled by default for all accounts.

      • Availability: These alternate dictionaries in italics are available in US English only.

      How to switch your dictionary

      To change your company's terminology to the owner or specialty contractor dictionary, contact your company's . They will work with your Procore point of contact to make the change.

Background

Use the steps below to change the status of multiple subcontractor payment applications at once.

Things to Consider

  • Required User Permissions

  • You can edit subcontractor payment application status in bulk only with the Payment Applications tool.

Prerequisites

Steps

  1. Navigate to the project's Payment Applications tool.

  2. Click the Subcontractor tab.

  3. Mark the tickboxes that correspond to the commitments with payment applications:

     Note

    To change the status of the selected payment applications in bulk, each commitment that you select must have a payment application.

    • To select all payment applications, mark the tickbox that corresponds to the heading in the status column. This selects all of the commitments in the list.

    • To select individual payment applications, mark the tickbox that corresponds to a commitment line item.

  4. Click Edit.

  5. Select the appropriate status from the Select a status drop-down list.
    Bulk Edit Sub Invoice Status

     Notes

  6. Click Save edits.
    Save Edits Sub Invoice

     Tip

    Why isn't the Save Edits button active? A payment application doesn't exist for one (1) or more of the selected commitment(s).

See Also