Sync Project level WBS codes to NetSuite®
Background
Company level WBS codes are pulled down onto a project in Procore. Each full WBS code on the project (cost code, cost type, custom segment) will be synced to Netsuite® as an item. The syncing of new WBS codes at the Project level code is triggered in the following ways:
The WBS code is used on a subcontractor payment application that is synced to Netsuite®.
The WBS code is added to the Procore Budget and a manual cost code sync is run.
Each Project level WBS code only needs to be synced once to create the Netsuite® item. The Netsuite® item will be a concatenation of the Procore project number + the WBS code. Once it is created via one of the above workflows, it is synced.
By design, the integration workflow for WBS codes will sync and create the Netsuite® item during subcontractor payment application export automaticallyif it has not already been synced previously. Generally, the only time you need to run a manual cost code sync is if you need the Netsuite® item before a subcontractor payment application is exported for that WBS code for the purposes of assigning direct cost transactions in Netsuite®.