Delete a main contract variation
Background
To delete or remove an MCV, you can click the Actions or the vertical ellipsis icon next to the MCV and select the Delete icon. However, when the icon is greyed out and not available, it means the MCV is associated with other item in Procore. The steps below show you how to remove associated item and then permanently delete an MCV.
Before you can perform a delete action, you must:
Change the status of the MCV from 'Approved' to another status as described below. If you want to change the status of multiple MCVs, you must apply the status changes in reverse order from how they were approved. For example, if you approved the PPCOs in sequential order (001, 002 and 003), you will need to remove the 'Approved' status in reverse order (003, 002, 001).
Unlink any Procore item associated with the MCV. This may include potential variations (PVs), variation requests (VRs) and payment applications as described in the prerequisites below.