Edit main contract payment applications
This page details the modernised main contract payment application experience.
This page details the modernised main contract payment application experience.
After creating a main contract payment application, you can open it using the Project level main contract or Payment Applications tool to edit as needed. The steps below show you how to edit a main contract payment application using the main contract tool.
Required User Permissions:
'Admin' level permissions on the project's main contract tool.
Additional Information:
You can only edit the most recently created payment application.
To learn how to use group row billing, see About Group row billing on main contract payment applications
Open a payment application
Update the general information
View a summary preview
Review & add approved changes
Update the bill of quantities
Set the column view for PDF exports
Search for matching line items
Manage custom groups
Manage table settings
Choose your editing method
Update the line items using the contract's accounting method
Upload attachments
Upload PDF backup from direct costs and payment applications in the selected valuation period
Upload attachments
Navigate to the project's main contract tool.
In the table, locate the contract to edit.
Looking for a specific payment application? To quickly find a match in a long list of payment applications, start typing in the Search box. Procore narrows the list to show only the payment applications that match your keywords.
Want to organise the payment applications in the owner list? To organise the payment application table, use the options in the Add group and Add filter menus. To learn more, see Search, filter and group payment applications.
Click the contract's Number link to open it.
Click the Payment applications tab.
Locate the payment application in the Payment applications (payment applications) tab.
Click the Payment application position or Payment application # link to open it.
Procore opens the payment application. You have different editing options on each card in the payment application.
To update the payment application's general information:
Scroll to General information.
Click Edit.
Update these fields as needed:
An asterisk (*) below indicates the field is required.

Status
Choose a status from the drop-down list. The default status of a new payment application is draft. See What are the default statuses for Procore payment applications?
Payment application no.
Change the payment application number, if appropriate.
Valuation period.*
Procore automatically populates the drop-down menu with the project's open valuation period. If there isn't an open valuation period, Procore selects the most recent valuation period.
Not seeing a menu option for the current valuation period? To learn how to create a valuation period, see Create valuation periods.
Period start
Procore automatically shows the start date of the selected valuation period.
Period end
Procore automatically shows the end date of the selected valuation period.
Click Save.
To preview the payment application in its finished layout:
Scroll to the Summary preview section.
Click the arrow to expand it.
If your team approves new budget change or main contract variations after a main contract payment application is created, a notification banner appears at the top of the payment application's Bill of Quantities.
If you want to add any newly approved changes to the most recent main contract payment application, follow these steps:
At the top of the Bill of Quantities, click Review & Add the notification banner. 
Don't see a notification banner? Either (1) there are no approved changes to add to the payment application or (2) the required 'budget changes' settings aren't configured. See Configure settings: Budget.
Can't click the Review & add button? Approved changes can only be added to a main contract's most recent payment application. If you are editing an older payment application, you can't click the Review & add button.
Are approved changes added to new main contract payment applications automatically? Yes. Approved changes are automatically added to the bill of quantities on a new payment application. You do not need to add approved changes to new main contract payment applications.
In the Review & add approved changes window, review the adjustment details.
Mark the tickboxes next to the changes to add.
Adding approved changes is a permanent action. Once added, they cannot be removed.

Choose from the options:
To add the selected changes, mark the tickboxes that correspond to the change and then, click Add.
A GREEN banner appears when the change is successfully added.
OR
To skip adding the changes, click Cancel.
Before updating the line items, it's helpful to understand the available editing methods. It's also important to know that the accounting method set on the main contract impacts which columns are available for data entry on the Bill of Quantities.
To update a bill of quantities:
View the bill of quantities in full screen
Set the column view for PDF exports
Search for matching line items
Manage custom groups
Manage table settings
Choose your editing method
Update the line items using the contract's accounting method
You can view the Bill of Quantities in full screen and close it when you finish your updates.
To open or close the full screen view of the Bill of Quantities:
Click the Open fullscreen link in the top-right corner of the Bill of Quantities.
OR
Click the Close fullscreen button to return to the card view.
You can configure the BOQ's column view before you export main contract payment applications.
Choose an option from the drop-down list:
Industry standard. This exports Procore's default column layout, which is compatible with most industry-standard form.
Current configuration. This exports your BOQ's current column view.
You can search for the matching line items to edit.
The scope of a search includes:
Budget Code
Description of work
To search for matching line item:
In the Search field, type a keyword or phrase.
Press the tab key or click the magnifying glass icon.
You can create, edit or delete custom grouping options. Once you've created your groups, you can apply them using the drop-down menu to the left of the 'Manage custom groups' button.
| Add, edit or delete custom groups
|
| Assign line items to custom groups
|
| Apply custom groupsApply the groups to the table using the drop-down menu to the left of the 'Manage custom groups' button. You have these options:
|
You can change the row height for the bill of quantities. You can also show or hide the columns that appear.
Click the Table settings button.
This opens the Table settings pane.
Under Row height, click one (1) option:
Small
medium
Large
Click the Table settings button.
This opens the Table settings pane.
Under Configure columns, choose from these options:
To show a column, move the toggle to the right.
To hide a column, move the toggle to the left.
To show all columns, click Show all. This is the default setting.
It's helpful to understand the differences between the two (2) available data entry methods for contracts. See How do I set the accounting method for a contract? Once you know the accounting method in place, click the Edit button to place the Bill of Quantities in editing mode. You can only edit the most recent payment application. If there is a more recent payment application, an informational message appears at the top of the Bill of Quantities.
The data entry requirements for line items on a Bill of Quantities are determined by the accounting method set on the payment application's main contract. In Procore, a main contract can be configured to use one (1) of two (2) accounting methods: Amount-based or Unit quantity based. The accounting method set on the main contract impact which columns are available for data entry on the Bill of Quantities. Once line items are created on a contract, all payment applications for that contract use the same accounting method. To learn more, see How do I set the accounting method for a contract or funding?
How do you know which accounting method is being used? An amount-based contract includes columns for entering pound and percentage amounts. A unit quantity based contract includes columns for entering a quantity and percentage amounts. Simply compare the columns in your payment application's Bill of Quantities to the ones in the examples below.
When creating a payment application, users have the option to place a mark in the Include backup from direct costs and payment applications in the selected valuation period box. The experience you see will depend on whether the setting is turned ON or OFF.
Include backup from direct cost and payment applications in the selected valuation period
Upload attachments
If the Include backup from direct costs and payment applications in the selected valuation period setting is turned ON.
Scroll to attachments.
Click Edit.
Scroll to the attachment card.
When the Include backup from direct cost and payment applications in the selected valuation period setting is turned ON, the attachment card contains these sections: Uploaded attachments, Attachments from subcontractor payment applications and Attachments from direct cost.

In the Uploaded attachments section, click the Upload attachments button.
Upload the desired attachment.
If the Include backup from direct costs and payment applications in the selected valuation period setting is turned OFF in the payment application.
Scroll to attachments.
Click Upload attachments.
Upload the desired attachment.