Create a potential variation from an RFI

Things to Consider

Prerequisites

Steps

  1. Navigate to the project's RFIs tool.

  2. Select the RFI from which you want to create the potential variation.

  3. Click Create potential VAR.

     Note
    • The Create potential VAR button is only visible and available when the prerequisites above have been satisfied.

    • The RFI information is used to populate the fields in the potential variation.

  4. Add or edit information as needed.

  5. Enter a description.

  6. Add an existing variation request, create a new variation request or do not attach a variation request.

  7. Add a change reason, who the request was received from, if there is a programme impact, location, who a reference is and any attachment. You can change the field change, paid in full and void options now or later.

  8. Click Create to save the PV without sending an email to members of the distribution list. Click Create and email to save the PV and send an email to members of the RFI distribution list.