Set up submittal programme calculations
Background
Submittal programme calculations is an optional configuration feature that can be enabled for use with the Project level Submittal tool. When enabled on a Procore project, this option analyses these key dates, which are entered by the creator under submittal programme information in a submittal package or a submittal item:
Required on-site date
Lead time
Design team review time
Internal review time
After analysing the date entry, Procore automatically populates the calculated date values for the end user in the following fields:
Planned return date
Planned internal review completed date
Planned submit by date
Based on the calculated date values above, Procore also suggests dates for the following fields:
Submitter due date
Approver due date
This helps the submittal creator ensure that submittal packages and items submitted to the review team are approved on schedule.
Things to Consider
Required User Permissions:
To create a submittal that uses these calculations, 'Standard' level permission to the Submittal tool.
To define the calculations used on the project, 'Admin' level permissions to the Submittals tool.
Prerequisite:
IMPORTANT! This feature must enabled in the Configure settings page. See Enable submittal programme calculations.
Additional Information:
Programme calculations do NOT automatically populate due dates in the submittal workflow.
Steps
Follow the steps in Create a submittal.
This reveals the new submittal page.Scroll down to the Submittal programme information area.
Set the following information:
Programme task. The programme task associated with the submittal being created. A programme must be uploaded to the project first. See Upload a Project Programme file to Procore's web application.
- Note: If you enter 7, the system subtracts '7' calendar day from the Planned return date to automatically populate the date entry for the Planned internal review completed date.
Design team review time. The number of days allotted for the design team's review on the submittal.
- Note: If you enter 10, the system subtracts '10' calendar day from the Required on-site date to automatically populate the date entry for the Planned return date.
Lead time. The expected number of calendar days that will be required for the material/services for the submittal to arrive.
Required on-site date. The date by which materials related to the work detailed on the submittal must be delivered and available at the construction site.
- N ote: If you enter 5, the system subtracts '5' calendar day from the Planned internal review completed date to automatically populate the date entry for the Planned submit by date.
Internal review time. The number of calendar days that your project's design team requires to ensure the submittal is properly reviewed.
Example:
See Also
Loading related articles...