Set up submittal programme calculations

Background

Submittal programme calculations is an optional configuration feature that can be enabled for use with the Project level Submittal tool. When enabled on a Procore project, this option analyses these key dates, which are entered by the creator under submittal programme information in a submittal package or a submittal item:

  • Required on-site date

  • Lead time

  • Design team review time

  • Internal review time

After analysing the date entry, Procore automatically populates the calculated date values for the end user in the following fields:

  • Planned return date

  • Planned internal review completed date

  • Planned submit by date

Based on the calculated date values above, Procore also suggests dates for the following fields:

  • Submitter due date

  • Approver due date

This helps the submittal creator ensure that submittal packages and items submitted to the review team are approved on schedule.

Things to Consider

  • Required User Permissions:

    • To create a submittal that uses these calculations, 'Standard' level permission to the Submittal tool.

    • To define the calculations used on the project, 'Admin' level permissions to the Submittals tool.

  • Prerequisite:

  • Additional Information:

    • Programme calculations do NOT automatically populate due dates in the submittal workflow.

Steps

  1. Follow the steps in Create a submittal.
    This reveals the new submittal page.

  2. Scroll down to the Submittal programme information area.

  3. Set the following information:

    1. Programme task. The programme task associated with the submittal being created. A programme must be uploaded to the project first. See Upload a Project Programme file to Procore's web application.

    2. Note: If you enter 7, the system subtracts '7' calendar day from the Planned return date to automatically populate the date entry for the Planned internal review completed date.

    3. Note: If you enter 10, the system subtracts '10' calendar day from the Required on-site date to automatically populate the date entry for the Planned return date.

    4. N ote: If you enter 5, the system subtracts '5' calendar day from the Planned internal review completed date to automatically populate the date entry for the Planned submit by date.

Example:

Create Submittal Schedule Info