Add a T&M Ticket to a Change Event
Background
When a T&M ticket involves a change in scope, you can add it directly to a change event. Doing so automatically links the ticket and its attachments to the change event's description while transferring all line items.
Aspectos a tener en cuenta
Las fichas de T y M y sus archivos adjuntos aparecen como hiperenlaces en el campo "Descripción" del evento extraordinario.
Formas alternativas de crear eventos extraordinarios:
Aprender a utilizar otras herramientas de Procore para crear un evento extraordinario.
Company Administrators can enable the Resource Management: Rate Tables - Company & Project Rate Management beta in Procore Explore. (US 2 | UK)
Rate tables centralize and standardize your labor and equipment rates across all projects.
When you create rate tables, you define cost and billable rates for labor and equipment. You can also define which rates can be overridden at the project level.
Rate tables are then applied to projects and referenced by different Procore tools such as Timesheets and Equipment. They can be viewed in 360 Reporting, Analytics, and within some Procore tools.
Las tarifas se configuran en las fichas de T y M y se aplican a las entradas de mano de obra, Equipos y Materiales. Cuando se crea un evento extraordinario a partir de una ficha de T y M, el precio unitario de ingresos en cada ítem de evento extraordinario se completa previamente en función de las tarifas de las entradas de tiempo y materiales.
Los Eventos extraordinarios aplican tasas solo a los materiales seleccionados del inventario.
Estas tasas de costo son visibles en el evento extraordinario en la herramienta Eventos extraordinarios.
Para proteger los datos históricos de cambios accidentales, las tasas creadas en la tabla se aplicarán al día siguiente.