Create Bulk Viewpoints

Background

You can automatically create viewpoints for each clash to provide consistency and streamline your workflow. You can create viewpoints for specific clash statuses, so that you can focus on the most important issues. Viewpoints are saved to a time-stamped folder, creating a clear record in time. You can create 3 different types of viewpoints: 3D View, Orient Plan View, and Isolate View.

Important

Pour utiliser Clash Manager de Procore pour Navisworks®, vous devez télécharger et installer le plug-in VDC de Procore et le plug-in BIM de Procore sur l’ordinateur Windows® exécutant votre logiciel de conception Autodesk®. Après l’installation, un onglet Procore et un bouton Gestionnaire de conflits apparaissent dans Autodesk® Navisworks®. Pour obtenir des directives, consultez Plug-ins Procore BIM.

Things to Consider

  • Required User Permissions:

    • 'Standard' or 'Admin' level permissions on the project's Coordination Issues tool.

  • Additional Information:

    • Best practice is to choose the folder structure for Assignment, then Test. Folders are created for individuals assigned with sub-folders for each clash test.

Steps

  1. Click Viewpoints in Clash Manager.

  2. Select the clash tests you want to create viewpoints for.

    • All Tests

    • Selected Tests to create viewpoints for the clash tests currently selected.

  3. Select how you want your viewpoints organized into folders.

    • Test: creates folder based on the clash test name

    • Assignment: creates folder based on the individual assigned

    • Status: creates folder based on the clash status

    • None: no folders created

  4. Select the viewpoint types to include.

  5. Select the clash statuses that you want to create viewpoints for.

  6. Click Create Viewpoints.
    Viewpoints appear in the Saved Viewpoints panel, organized as specified.