Sync CI Changes

Sync coordination issues to keep both Procore and Navisworks® up-to-date. The smoother workflow reduces errors and manual work. When both systems are updated, the responsible person is clear and accountable.

Important

Pour utiliser Clash Manager de Procore pour Navisworks®, vous devez télécharger et installer le plug-in VDC de Procore et le plug-in BIM de Procore sur l’ordinateur Windows® exécutant votre logiciel de conception Autodesk®. Après l’installation, un onglet Procore et un bouton Gestionnaire de conflits apparaissent dans Autodesk® Navisworks®. Pour obtenir des directives, consultez Plug-ins Procore BIM.

Things to Consider

  • Required User Permissions:

    • 'Admin' level permissions on the project's Coordination Issues tool.

Steps

  1. Click Sync CI Changes in Clash Manager.

  2. Review the changes.

  3. Select the coordination issues you want to sync.

  4. Click Sync Selected.