終了ステップを追加 (成功)

Configure the 'End Step (Successful)' in the Workflow Builder to formally mark a workflow's successful completion. Add the step, define its name and status, and set up optional notifications to inform relevant stakeholders.

Steps

Add an End Step (Successful)

An End Step (Successful) concludes the workflow and signifies a successful outcome. For example, a project item is 'Approved' or 'Approved as Noted.'

  1. In the Workflow Builder, click Icon Blue Plus Pfcp in an existing step and choose End Step (Successful).

  2. Under General Information, do the following:

    • Step Name. Enter a name for the workflow step.

    • Item Status. Select the status that shows successful completion. Status options vary for each item in the Procore tool.

    • Optional: Notification Recipients . Select which groups or roles Procore will automatically notify when the step is complete. The selections include:

  3. Click one (1) of these options:

    • Cancel. Discards any changes made.

    • Save as Draft. Saves a 'Draft' version with a minor version number (e.g., 0.1, 0.2, 0.3, and so on). Select this option if the workflow template is still under development.

    • Save and Publish. Creates a major version number for the workflow (e.g., 1.0, 2.0, 3.0, and so on). Choose this option when the workflow is ready for implementation and project assignment.

Save the Template

大事な

Procore では、ワークフロー テンプレートを作成する際に [ 草案として保存 ] オプションを使用して進行状況を保存することを強くお勧めします。これは、偶発的な終了、ブラウザの問題、またはその他の予期しない中断によるデータ損失を最小限に抑えるための標準的なベスト プラクティスです。

  • Cancel. Discards any changes made.

  • Save as Draft. Saves a 'Draft' version with a minor version number (e.g., 0.1, 0.2, 0.3, and so on). Select this option if the workflow template is still under development.

  • Save and Publish. Creates a major version number for the workflow (e.g., 1.0, 2.0, 3.0, and so on). Choose this option when the workflow is ready for implementation and project assignment.