Sync CI Changes

Sync coordination issues to keep both Procore and Navisworks® up-to-date. The smoother workflow reduces errors and manual work. When both systems are updated, the responsible person is clear and accountable.

Important

To use Procore Clash Manager for Navisworks® on a Windows® computer running your Autodesk® software, see Download & Install the Procore BIM Plugin.

Things to Consider

  • Required User Permissions:

    • 'Admin' level permissions on the project's Coordination Issues tool.

Steps

  1. Click Sync CI Changes in Clash Manager.

  2. Review the changes.

  3. Select the coordination issues you want to sync.

  4. Click Sync Selected.