Considerations
Here are some important things to know about Direct Cost Exports to ERP:
Permissions & Prerequisites
Before managing direct cost exports, ensure you have the correct permissions and roles assigned.
Required Tool: Company-Level Direct Costs tool.
Required User Permissions:
To manage uploads, view all company-wide direct costs across all projects in the Uploads tab, and execute ERP exports via the 'Send to ERP' action, 'Standard' or 'Admin' level permissions on the Company level Direct Costs tool.
To review and code direct costs only on the projects you’re assigned to, without seeing direct costs across the whole company:
‘Read Only’ level permissions on the Company level Direct Costs tool.
AND
Assignment on the project to a role that your company has set up as a reviewer role in the Company level Direct Costs tool’s configuration settings.
If exporting to Sage Intacct:
Ensure the PC non-commitment transaction definition is configured. See Sage Intacct® Setup Guide - Direct Cost Export Setup.
Current Supported ERP Integrations
CMiC
QuickBooks® Desktop
QuickBooks® Online
Sage 100 Contractor®
Sage 300 CRE®
Sage Intacct®
Vista®
Workday®
Limitations
Please note the following limitations regarding exports in this Beta version:
Multi-Project Invoice Export Coding: A single invoice cannot be split and coded across multiple projects for export within the tool.
Workaround: Enter the invoice multiple times for each project before exporting. For example, for a $1,000 invoice split between two projects, upload it once for $300, and upload it a second time for $700 (appending a letter such as 'B' to the end of the invoice number).
Manual Accounting Date for ERP Posting: Accounting Date currently requires manual entry to establish the financial posting period (auto-populating to match invoice date is planned).
Third-Party Integrations: Custom or third-party ERP integrations must explicitly account for the tool origin filter to prevent cost duplication post-export.